Inspection Status: Approved
Inspection History: STORMWATER FOLLOW-UP INSP
Permit Number - T09BU00522
Inspection Description - STORMWATER FOLLOW-UP INSP
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/03/2020 | STORMWATER FOLLOW-UP INSP | Approved | ||
04/22/2010 | STORMWATER FOLLOW-UP INSP | Continued | NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME | |
03/23/2010 | STORMWATER FOLLOW-UP INSP | Continued | INFRUSTRUCTURE IN, UNDEVELOPED LOTS HAVE BEEN STABILIZED, NO SIGNIFICANT STORM WATER CONCERN AT THIS TIME | |
03/11/2010 | STORMWATER FOLLOW-UP INSP | Continued | NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME. MET W/CONTRACTOR ON SITE TO DISCUSS CONCRETE SWALE BEING CONSTRUCTED ALONG EAST PERIMETER. CHANGE TO OUTLET OF SWALE TO INCLUDE SCUPPERS BEING INSTALLED UNDER SIDEWALK. CHANGE HAS BEEN APPROVED BY COT AND THE EOR. |
|
01/13/2010 | STORMWATER FOLLOW-UP INSP | Continued | NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME. SITE IS UNDER A STORM WATER PERMIT UNTIL THE SITE IS 100% STABILIZED AND UNDEVELOPED LOTS ARE HYDROSEEDED AND/OR ROCKED. | |
12/14/2009 | STORMWATER FOLLOW-UP INSP | Continued | ACCESSIBLE ROUTE OFF OF PIMA, RUN SLOPE MUST BE LESS THAN 5% OR ROUTE MUST COMPLY W/ HC RAMP REQUIREMENTS. SLOPE ALONG RIGHT OF WAY MUST BE STABILIZED. STORM WATER CONCERNS OK | |
11/16/2009 | STORMWATER FOLLOW-UP INSP | Continued | NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME | |
10/29/2009 | STORMWATER FOLLOW-UP INSP | Continued | 1) ENSURE YOU CONTIN TO PERFORM, AND DOCUMENT STORM WATER SELF INSPECTIONS PER YOUR PLAN 2) MAINTAIN YOUR STORM WATER CONTROLS THROUGHOUT THE DURATION OF THE PROJECT. 3) CONTINUE TO SWEEP UP TRACKED MATERIALS OFF OF PUBLIC ROADWAYS. |
|
09/09/2009 | STORMWATER FOLLOW-UP INSP | Continued | SOME TRACKING OF SOIL ON RAODWAYS, CONT TO SWEEP ROUTINELY. NO OTHER STORM WATER CONCERNS AT THIS TIME | |
08/20/2009 | STORMWATER FOLLOW-UP INSP | Continued | NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME | |
08/05/2009 | STORMWATER FOLLOW-UP INSP | Correction Required | 1) SWEEP UP TRACKED SOIL OFF OF ALVERNON MORE OFTEN. 2) ENSURE SILT SOCK INSTALLED IS MAINTAINED - REPAIR DAMAGED AREAS AND/OR REPLACE AS NEEDED. 3) RE-INSTALL SEDIMENT CONTROLS ALONG THE NORTH PERIMETER OF THE SITE. CORRECT BY 10 WORKING DAYS/NON-COMPLIANCE WILL RESULT IN A NOTICE OF VIOLATION |