Inspection Status: Approved
Inspection History: GRADING - INTERMEDIATE
| Date |
Description |
Inspector |
Results |
Comments |
| 06/28/2011 |
GRADING - INTERMEDIATE |
|
Approved |
Approved |
| 12/16/2010 |
GRADING - INTERMEDIATE |
|
Continued |
Contractor finishing work along Camino Camprestre. Frontage along Country Club is complete except for final clean up and stabilization of disturbed areas. |
| 10/13/2010 |
GRADING - INTERMEDIATE |
|
Continued |
Work continues on sidewalks and street lights |
| 08/10/2010 |
GRADING - INTERMEDIATE |
|
Continued |
Frontage improvements continue along Camprestre. |
| 07/14/2010 |
GRADING - INTERMEDIATE |
|
Continued |
Contractor working on placing irrigation pipe along 22nd |
| 03/18/2010 |
GRADING - INTERMEDIATE |
|
Partial Approval |
Pouring curb along Camino Camprestre, and curb ramps along Country Club. |
| 03/11/2010 |
GRADING - INTERMEDIATE |
|
Partial Approval |
Checked slope on new curb ramps off of Country Club and Camino Campestre. Both OK. |
| 03/04/2010 |
GRADING - INTERMEDIATE |
|
Continued |
work continuing on retaing walls along broadway, and crubing along north edge of park. |