Permit: T09BU00493

Parcel: 10509546C


Addresses:

68 W RIVER RD


Inspection Status: Approved

Inspection History: GRADING - INTERMEDIATE

Permit Number - T09BU00493

Inspection Description - GRADING - INTERMEDIATE

Inspection Status - Approved

Date Description Inspector Results Comments
11/18/2011 GRADING - INTERMEDIATE Approved
10/31/2011 GRADING - INTERMEDIATE Continued WALKED SITE, SITE IS 80% STABILIZED. SOME SITE WORK LEFT TO BE COMPLETED.
NEED CERT STATEMENT FROM THE ENG OF RECORD PRIOR TO FINAL APPROVAL.
10/12/2011 GRADING - INTERMEDIATE Continued 1) A COPY OF THE SITE NOI HAS BEEN POSTED ON SITE.
2) A STABILIZED ENTRANCE HAS BEEN INSTALLED.
3) THE MAJORITY OF SITE IS PAVED - A COUPLE SECTIONS LEFT TO BE DONE.
4) A CONCRETE WASH OUT IS ON SITE.
5) ENSURE TRACKING IS SWEPT ROUTINELY AND SELF INSPECTIONS ARE DOCUMENTED.
09/29/2011 GRADING - INTERMEDIATE Violation NOTICE OF VIOLATION WAS ISSUED AFTER FOLLOW UP STORM WATER INSPECTION TO CORRECT NON-COMPLIANCE WITH THE APPROVED STORM WATER PLAN.
1) NO COPY OF THE SIGNED NOI POSTED AT THE ENTRANCE TO THE SITE.
2) NO DESIGNATED CONCRETE WAS OUT ON SITE.
3) NO STABILIZED CONSTRUCTION ENTRANCE/EXIT ON SITE

COMPLY WITHIN 7 WORKING DAYS
09/23/2011 GRADING - INTERMEDIATE Correction Required 1) CLEAN UP SOIL OFF OF THE EAST SIDE OF THE PROJECT.
2) CLEAN UP WASTE CONCRETE/STUCCO/PAINT ALONG THE EAST SIDE OF THE PROJECT.
3) POST A COPY OF YOUR NOI AT THE ENTRANCE TO THE SITE.
4) PROVIDE A DESIGNATED CONCRETE/MATERIALS CLEAN OUT ON SITE.
5) ENSURE ALL OF THE STORM DRAIN PIPING HAS BEEN VERIFIED BY THE CITY OF TUCSON AND/OR YOUR ENGINEER OF RECORD.
6) RE-ESTABLISH YOUR ROCK ENTRANCE/EXIT
7) SWEEP UP TRACKING OFF PUBLIC ROADWAY.
09/06/2011 GRADING - INTERMEDIATE Continued 1) ENSURE YOUR CONSTRUCTION ENTRANCE/EXIT IS MAINTAINED - RE-ESTABLISHED/ADD ROCK AS NECESSARY
2) SWEEP UP TRACKING OF SOIL OF PUBLIC ROADWAYS ROUTINELY.
3) MAINTAIN/RE-ESTABLISH SEDIMENT CONTROLS ALONG THE PERIMETER -REPLACE AS NECESSARY
4) ENSURE A DESIGNATED CONCRETE WASH OUT IS INSTALLED AS REQUIRED
08/22/2011 GRADING - INTERMEDIATE Continued 1) PROVIDE VERIFICATION OF UNDERGROUND STORM PIPE (SIZE, MATERIAL, GRADE) FROM THE ENGINEER OF RECORD.
2) PROVIDE PICTURES OF STORM PIPE/MANHOLE TRANSITION.
3) ADD SUPPLEMENTAL CONTROLS (WADDLE) ALONG SE CORNER OF SITE IN FRONT OF EXISTING STORM CATCH BASIN.
4) VERIFIED FORM AND LAYOUT OF CURB AND GUTTER ALONG NORTH SIDE.
4) CONTINUE TO SWEEP UP TRACKED SOIL OFF PUBLIC ROADWAYS.
5) KEEP DISTURBED SOIL FROM CONSTRUCTION SITE OUT OF EXISTING STORM WATER CATCH BASIN
07/21/2011 GRADING - INTERMEDIATE Continued 1) CLOSE GAPS IN WADDLE (SILT SOCK) ALONG EAST PERIMETER.
2) ADD ROCK TO CONSTRUCTION ENTRANCE/EXIT AT EAST SIDE OF SITE.
3) SWEEP UP TRACKED SOIL OFF PUBLIC ROADWAY AT ENTRANCE/EXIT
4) ADD SILT SOCK ALONG EAST SIDE OF EXISTING DRAINAGE CHANNEL.
5) CONTRACTOR HAS INSTALLED FUEL TANKS AND IS WORKING ON UTILITY CONNECTIONS
07/01/2011 GRADING - INTERMEDIATE Continued Contractor began site work today, removing asphalt and installing utilities.