Inspection History: GRADING - INTERMEDIATE
Permit Number - T09BU00446
Inspection Description - GRADING - INTERMEDIATE
Inspection Status - Approved
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/23/2010 | GRADING - INTERMEDIATE | Approved | Approved | |
| 01/22/2010 | GRADING - INTERMEDIATE | Partial Approval | Complete item #2 of final punch list and submit asbuilt /final site plan. | |
| 01/04/2010 | GRADING - INTERMEDIATE | Partial Approval | Prelim walk through with super, needs to seed disturbed areas, scarify basin bottoms, remove construction debris add bollards where required per plan, grade around outlet pipes in basins. | |
| 12/02/2009 | GRADING - INTERMEDIATE | Continued | Walked site with super, paving underway 50% complete. Access route from street was being poured, I checked slope and it was off, contractor said he would fix prior to finishing conc. Discuss need for as-builts and eng.Cert for basins. |
|
| 11/16/2009 | GRADING - INTERMEDIATE | Continued | Grading for parking lot underway | |
| 10/22/2009 | GRADING - INTERMEDIATE | Continued | Discuss relocation of drain scupper to exit curb at different location, I approved in field. | |
| 10/13/2009 | GRADING - INTERMEDIATE | Continued | Curb begining to go in, minor site grading | |
| 09/14/2009 | GRADING - INTERMEDIATE | Continued | Work continuing on building, no additional work on site at this time. | |
| 08/17/2009 | GRADING - INTERMEDIATE | Continued | Building under construction, no further work on site. | |
| 08/06/2009 | GRADING - INTERMEDIATE | Continued | Storm basins roughed in, building pad footings under construction. footing for retaining wall along north wash underconstruction. | |
| 07/27/2009 | GRADING - INTERMEDIATE | Continued | clearing complete working on building pad. Contractor will have special inspector perform compaction test on pad and footings |