Inspection Status: Approved
Inspection History: GRADING - INTERMEDIATE
Permit Number - T09BU00399
Inspection Description - GRADING - INTERMEDIATE
Inspection Status - Approved
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/15/2010 | GRADING - INTERMEDIATE | Approved | ||
| 06/11/2010 | GRADING - INTERMEDIATE | Continued | MINOR CHANGE TO SIDEWALK LOCATION FOR PED ACCESS FROM STREET TO BLDG, ENSURE RUN SLOPE NO GREATER THAN 5%. SITE WORK APPROXIMATELY 75% COMPLETE, SITE IS STABILIZED, LANDSCAPE 80% DONE. NO OTHER CHANGES OR CONCERNS WITH APPROVED GRADING PLAN. PROVIDE RET/DET, DRAINAGE CERT STATEMENT FROM THE ENGINEER OF RECORD FOR FINAL. |
|
| 05/25/2010 | GRADING - INTERMEDIATE | Continued | 1) PROVIDE A DESIGNATED CONCRETE WASH OUT ON SITE PER YOUR STORM WATER PLAN. 2) SWEEP UP TRACKED SOIL OFF PUBLIC ROADWAY AND OUT OF CURB LINE AND BACK ON SITE. 3) CALL FOR INSPECTION FOR ANY CHANGES TO THE SITE WORK DIFFERENT FROM THE APPROVED GRADING/SITE PLAN. |
|
| 04/19/2010 | GRADING - INTERMEDIATE | Continued | 4" PVC ROOF DRAIN PIPE INSTALLED AT EACH COLUMN, PIPES BRANCH INTO 8" MAIN LINE. 3 CLEAN OUTS FOR LINE. PIPE INVERT AT BOTTOM OF RET/DET BASIN AND 3'X7' TRENCH W/ ROCK AND FILTER FABRIC. | |
| 03/30/2010 | GRADING - INTERMEDIATE | Continued | LOOKED AT RE-BAR LAYOUT FOR SCREEN WALLS ALONG PEIMETER AND TRASH ENCLOSURE. ROOF DRAIN FOR GAS ISLAND TIES INTO RET/DET BASIN W/ A ROCK DRAINAGE CHANNEL THROUGH THE MIDDLE. INV. OF 8" ROOF DRAIN IS ALMOST 4' BELOW BOTTOM OF BASIN. NO STORM WATER CONCERNS |
|
| 03/16/2010 | GRADING - INTERMEDIATE | Continued | 1) CONTRACTOR IS WORKING ON CURB AND GUTTER ALONG NORTH/NORTHEAST SIDE OF SITE PER SPECS ON PLAN. 2) GASOLINE AREA AWNING IN PLACE 3) UNDERGROUND STORAGE TANKS IN PLACE 4) NEED TO KEEP UP ON TRACKING, SITE IS WET AND SOME CONSTRUCTION VEHICLE TRACKING HAS OCCURED 5) FOOTER FOR BLDG HAS BEEN POURED |