Inspection History Details
Inspection Status: Approved
Inspection History: GRADING - INTERMEDIATE
Permit Number - T09BU00361
Inspection Description - GRADING - INTERMEDIATE
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/07/2010 | GRADING - INTERMEDIATE | Approved | RPM installed | |
11/19/2009 | GRADING - INTERMEDIATE | Partial Approval | Chwecked site all work appears to be complete, will ask contractor to call for final grading inspection. | |
10/02/2009 | GRADING - INTERMEDIATE | Partial Approval | Signs installed, seal coat being installed today, still need stripping. | |
09/14/2009 | GRADING - INTERMEDIATE | Partial Approval | no activity today, sign locations staked, stripping layout complete. | |
09/01/2009 | GRADING - INTERMEDIATE | Partial Approval | All grading activity complete and hydroseed placed waiting for stripping and signs, and final as-builts. | |
08/26/2009 | GRADING - INTERMEDIATE | Partial Approval | Contractor prep for hydosedding will aplly today. | |
08/21/2009 | GRADING - INTERMEDIATE | Partial Approval | Contractor raising valve boxes, epoxy placed in all rebar holes for extruded curbing. | |
08/18/2009 | GRADING - INTERMEDIATE | Partial Approval | Contractor dressing up project and nstalling drainage swale, tlaked to super about final stabilization they want to hydroseed and use soil stabilization over furture building pad. Will check on different products for soil stabilization and get back to me. Asked to blow out vertical holes in curb before appling apoxy to rebar. |
|
08/13/2009 | GRADING - INTERMEDIATE | Partial Approval | Paving complete on west road, contractor will begin final grading of median on Monday | |
08/12/2009 | GRADING - INTERMEDIATE | Partial Approval | Paving west road today, spoke to DOWL eng. today about vertical rebar placement in curb not to detail, he said he would review and get a detail of any changes. | |
08/11/2009 | GRADING - INTERMEDIATE | Partial Approval | Subgrade for west entrance Rd ready for paving, told super that vertical rebar in extruded curb did not meet plans, they are placed at 10ft OC plans call for 4 ft OC, he will check with engineer. | |
08/07/2009 | GRADING - INTERMEDIATE | Partial Approval | AB placed on west side of entrance road, contractor grading for pavement on Tuesday. Curb placed on east side of road. | |
08/05/2009 | GRADING - INTERMEDIATE | Partial Approval | Inspected extruded curb installation on east road, AB placed on west road, contractor to place asphalt on Tuesday 8/11 | |
07/30/2009 | GRADING - INTERMEDIATE | Partial Approval | Grading west side of approach road, valley gutter on west aproach formed. | |
07/20/2009 | GRADING - INTERMEDIATE | Partial Approval | Paved east side of road on Friday, will begin to remove existing asphalt on west side of road tomorrow. | |
07/16/2009 | GRADING - INTERMEDIATE | Partial Approval | AB placed and graded to hubs, OK to pave starting tomorrow. | |
07/14/2009 | GRADING - INTERMEDIATE | Continued | All AB placed contractor will pave east portion of road on Friday 7/17. | |
07/10/2009 | GRADING - INTERMEDIATE | Continued | rough grading on east side of road complete, compaction test OK, contractor will start to place AB next week | |
06/30/2009 | GRADING - INTERMEDIATE | Continued | Checked for storm controls, all in place |