Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T09BU00361

Parcel: 20914001C


Addresses:

9700 W AJO HY


Inspection Status: Approved

Inspection History: GRADING - INTERMEDIATE

Permit Number - T09BU00361

Inspection Description - GRADING - INTERMEDIATE

Inspection Status - Approved

Date Description Inspector Results Comments
01/07/2010 GRADING - INTERMEDIATE Approved RPM installed
11/19/2009 GRADING - INTERMEDIATE Partial Approval Chwecked site all work appears to be complete, will ask contractor to call for final grading inspection.
10/02/2009 GRADING - INTERMEDIATE Partial Approval Signs installed, seal coat being installed today, still need stripping.
09/14/2009 GRADING - INTERMEDIATE Partial Approval no activity today, sign locations staked, stripping layout complete.
09/01/2009 GRADING - INTERMEDIATE Partial Approval All grading activity complete and hydroseed placed waiting for stripping and signs, and final as-builts.
08/26/2009 GRADING - INTERMEDIATE Partial Approval Contractor prep for hydosedding will aplly today.
08/21/2009 GRADING - INTERMEDIATE Partial Approval Contractor raising valve boxes, epoxy placed in all rebar holes for extruded curbing.
08/18/2009 GRADING - INTERMEDIATE Partial Approval Contractor dressing up project and nstalling drainage swale, tlaked to super about final stabilization they want to hydroseed and use soil stabilization over furture building pad. Will check on different products for soil stabilization and get back to me.
Asked to blow out vertical holes in curb before appling apoxy to rebar.
08/13/2009 GRADING - INTERMEDIATE Partial Approval Paving complete on west road, contractor will begin final grading of median on Monday
08/12/2009 GRADING - INTERMEDIATE Partial Approval Paving west road today, spoke to DOWL eng. today about vertical rebar placement in curb not to detail, he said he would review and get a detail of any changes.
08/11/2009 GRADING - INTERMEDIATE Partial Approval Subgrade for west entrance Rd ready for paving, told super that vertical rebar in extruded curb did not meet plans, they are placed at 10ft OC plans call for 4 ft OC, he will check with engineer.
08/07/2009 GRADING - INTERMEDIATE Partial Approval AB placed on west side of entrance road, contractor grading for pavement on Tuesday. Curb placed on east side of road.
08/05/2009 GRADING - INTERMEDIATE Partial Approval Inspected extruded curb installation on east road, AB placed on west road, contractor to place asphalt on Tuesday 8/11
07/30/2009 GRADING - INTERMEDIATE Partial Approval Grading west side of approach road, valley gutter on west aproach formed.
07/20/2009 GRADING - INTERMEDIATE Partial Approval Paved east side of road on Friday, will begin to remove existing asphalt on west side of road tomorrow.
07/16/2009 GRADING - INTERMEDIATE Partial Approval AB placed and graded to hubs, OK to pave starting tomorrow.
07/14/2009 GRADING - INTERMEDIATE Continued All AB placed contractor will pave east portion of road on Friday 7/17.
07/10/2009 GRADING - INTERMEDIATE Continued rough grading on east side of road complete, compaction test OK, contractor will start to place AB next week
06/30/2009 GRADING - INTERMEDIATE Continued Checked for storm controls, all in place