Inspection History Details
Inspection Status: Approved
Inspection History: STORMWATER FOLLOW-UP INSP
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/27/2010 | STORMWATER FOLLOW-UP INSP | Approved | ||
| 12/31/2009 | STORMWATER FOLLOW-UP INSP | Continued | MOST SITE WORK COMPLETED NEED TO FINISH DRAINAGE AT REAR OF BLDG. NEED BASIN/DRAINAGE CERT LETTER FROM EOR. NEED TO REMOVE STOCKPILED MATERIAL. NO STORM WATER CONCERNS AT THIS TIME |
|
| 12/16/2009 | STORMWATER FOLLOW-UP INSP | Continued | CONTRACTOR PLACED SEDIMENT CONTROLS AROUND STOCKPILED MATERIAL ALONG WEST SIDE OF PROJECT. NO OTHER STORM WATER CONCERNS AT THIS TIME | |
| 12/10/2009 | STORMWATER FOLLOW-UP INSP | Correction Required | SPOKE W/ SUPINTENDENT ABOUT STOCKPILE LOCATED TO THE SW OF THE SITE, HE STATED THAT IT WILL BE REMOVED WITH IN 2 WEEKS. CONTRCATOR SHOULD PLACE TEMP SEDIEMNT CONTROLS AROUND STOCKPILE UNTIL REMOVED |
|
| 10/23/2009 | STORMWATER FOLLOW-UP INSP | Continued | CONTRACTOR INSTALLED APPROXIMATELY 91' OF 12" PVC STORM DRAIN PIPING AND CONNECTED IT TO A 36" CONCRETE BUBBLER BOX. PIPE TRENCH WAS BEDDED AND COMPACTED, CONCRETE BUBBLER HAS 48" OF ROCK W/FILTER FABIC IN BOTTOM OF PIPE. CONTRACTOR INSTALLED 40' OF 8" PVC STORM DRAIN PIPE CONNECTED TO BLDG ROOF DRAIN AT NW CORNER OF BLDG. NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME |
|
| 09/29/2009 | STORMWATER FOLLOW-UP INSP | Continued | SEDIMENT CONTROLS HAVE BEEN INSTALLED. CONTRACTOR WILL INSTALL A DESIGNATED CONCRETE/MATERIALS WASH OUT WHEN APPLICABLE. CONTRACTOR MUST MAINTAIN SED CONTROLS THROUGHOUT THE DURATION OF THE PROJECT. CONTINUE TO SWEEP UP TRACKIN |