Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit: T09BU00297

Parcel: 12112056C


Addresses:

5151 E SPEEDWAY BL

Inspection Status: Approved

Inspection History: STORMWATER FOLLOW-UP INSP

Date Description Inspector Results Comments
01/27/2010 STORMWATER FOLLOW-UP INSP Approved
12/31/2009 STORMWATER FOLLOW-UP INSP Continued MOST SITE WORK COMPLETED NEED TO FINISH DRAINAGE AT REAR OF BLDG. NEED BASIN/DRAINAGE CERT LETTER FROM EOR. NEED TO REMOVE STOCKPILED MATERIAL.
NO STORM WATER CONCERNS AT THIS TIME
12/16/2009 STORMWATER FOLLOW-UP INSP Continued CONTRACTOR PLACED SEDIMENT CONTROLS AROUND STOCKPILED MATERIAL ALONG WEST SIDE OF PROJECT. NO OTHER STORM WATER CONCERNS AT THIS TIME
12/10/2009 STORMWATER FOLLOW-UP INSP Correction Required SPOKE W/ SUPINTENDENT ABOUT STOCKPILE LOCATED TO THE SW OF THE SITE, HE STATED THAT IT WILL BE REMOVED WITH IN 2 WEEKS.
CONTRCATOR SHOULD PLACE TEMP SEDIEMNT CONTROLS AROUND STOCKPILE UNTIL REMOVED
10/23/2009 STORMWATER FOLLOW-UP INSP Continued CONTRACTOR INSTALLED APPROXIMATELY 91' OF 12" PVC STORM DRAIN PIPING AND CONNECTED IT TO A 36" CONCRETE BUBBLER BOX. PIPE TRENCH WAS BEDDED AND COMPACTED, CONCRETE BUBBLER HAS 48" OF ROCK W/FILTER FABIC IN BOTTOM OF PIPE.
CONTRACTOR INSTALLED 40' OF 8" PVC STORM DRAIN PIPE CONNECTED TO BLDG ROOF DRAIN AT NW CORNER OF BLDG.
NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME
09/29/2009 STORMWATER FOLLOW-UP INSP Continued SEDIMENT CONTROLS HAVE BEEN INSTALLED.
CONTRACTOR WILL INSTALL A DESIGNATED CONCRETE/MATERIALS WASH OUT WHEN APPLICABLE.
CONTRACTOR MUST MAINTAIN SED CONTROLS THROUGHOUT THE DURATION OF THE PROJECT.
CONTINUE TO SWEEP UP TRACKIN