Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T09BU00173

Parcel: 12810076B


Addresses:

384 S WILLIAMS BL


Inspection Status: Approved

Inspection History: GRADING - INTERMEDIATE

Permit Number - T09BU00173

Inspection Description - GRADING - INTERMEDIATE

Inspection Status - Approved

Date Description Inspector Results Comments
09/15/2011 GRADING - INTERMEDIATE Approved Approved
09/08/2011 GRADING - INTERMEDIATE Correction Required Looked at LS areas and WH areas today, they need to be depressed as shown on the plans so that the proper amount of storage is achieved. Will recheck tomorrow.
07/26/2011 GRADING - INTERMEDIATE Continued Met with contractor and discussed placement of sidewalk scuppers, thet will add 1 or 2 to insure proper drainage, also discussed access for HC in front of building. may have to replace a section of curb for slope.
07/18/2011 GRADING - INTERMEDIATE Continued Contractor excavating for WH areas in parking lot, and Storm basin.
07/06/2011 GRADING - INTERMEDIATE Continued Contractor began ex for water harvest areas.
06/27/2011 GRADING - INTERMEDIATE Continued Contractor will begin to grade for WH basins this week.
06/08/2011 GRADING - INTERMEDIATE Continued work continuing on building na dsewer in street.
05/05/2011 GRADING - INTERMEDIATE Correction Required Contractor has placed roll off storage containers and stockpiles dirt on adjacent property with permission from owner. I told contractor that they will have to stabilize this are when project is complete, and the property owner needs to get a TUP for the site.
04/21/2011 GRADING - INTERMEDIATE Continued Work continuing on building, no site work today.
04/13/2011 GRADING - INTERMEDIATE Continued Asphalt in place, curb cuts marked out.
03/29/2011 GRADING - INTERMEDIATE Continued COntractor has cut asphalt for paving along North access road, contractor not on site, super not onsite I could not verify location.
03/22/2011 GRADING - INTERMEDIATE Continued Met with contractor to discuss curb height and asphalt grades away from new curb along the North side of building, we will try and mainatain a max 8.25" revel on curb and meet the max slope of the PAAL of 5.9% as shown on plans. Contractor will layout in field for another inspection prior to paving.
03/07/2011 GRADING - INTERMEDIATE Continued Working on block wall for dumpster area, testing storm pipe in front of building
02/28/2011 GRADING - INTERMEDIATE Continued Framing begun on building, testing storm line along North side of building.
02/11/2011 GRADING - INTERMEDIATE Continued Contractor paving south parking lot today, and pouring dumpster enclouser
02/08/2011 GRADING - INTERMEDIATE Continued Contractor placing AB for parking lot, will pave on Thursday, still working on a resolution for the grade difference at front of bldg and existing PAAL.
01/31/2011 GRADING - INTERMEDIATE Continued Met with contractor to discuss conflict between the lid on the grease interceptor and the sidewalk, the lid will protrude out into the curb and drive isle by 6 " and be above the asphalt grade by 2", we discussed options and the contractor will probably over lay lid with asphalt and blend into the drive asile.
01/26/2011 GRADING - INTERMEDIATE Continued Work continues on building pad and installation of fire line to building.
01/24/2011 GRADING - INTERMEDIATE Continued Pipe work backfilled and on hold for now until power is reolcated so that final tie in can occur.
01/21/2011 GRADING - INTERMEDIATE Continued OK to backfill 12" HDP pipe on soulth side of building to drain basin # 7
01/19/2011 GRADING - INTERMEDIATE Approved Contractor placing 12" HDP pipe south of building from basin to drain basin #7, OK to backfill first approx. 150ft, will inspect remainder tomorrow when finished with installation.
01/14/2011 GRADING - INTERMEDIATE Continued OK to backfill 10"HDP pipe from NE corner of building to storm basin, OK to backfill 60 ft of 12" HDP pipe from basin toward street.
01/13/2011 GRADING - INTERMEDIATE Partial Approval Looked at the 12" HDP pipe on the south side of building today, pipe in trench but not shaded, checked on flow line with plans and looks OK.
01/12/2011 GRADING - INTERMEDIATE Partial Approval OK to backfill 12 HDP pipe along North edge of building.
01/05/2011 GRADING - INTERMEDIATE Continued EOR has been by the site and is working on outlet for strom drain. Will contact TEP to determine if existing conduit can be flexed enough to allow storm pipe to run over the top of conduit.
12/28/2010 GRADING - INTERMEDIATE Continued Still no resolution to pipe conflic issue, contractor work on utilities for building pad.
12/22/2010 GRADING - INTERMEDIATE Continued Grading activities have come to a hault waiting for EOR to advise on outfall conflict with existing undergroud utilities. No storm pipe has been placed, trench is dug.
12/20/2010 GRADING - INTERMEDIATE Continued Conflict with existing utilities at the storm pipe outfall on Williams Blvd. POwer, gas and phone are all at or near pipe grade, Contractor has sent sketch to EOR for resolution.
12/17/2010 GRADING - INTERMEDIATE Continued Spoke to contractor about the CB that flows from site into the city CB on Williams, problem with the grade makes it very tight to get a ring and cover on, contractor will change to a flat lid, I told him to have EOR approve change.
12/09/2010 GRADING - INTERMEDIATE Continued Contractor has building pad and parking lot rough graded, beginning work on detention basin, will begin storm pipe next week, and curb work.
11/29/2010 GRADING - INTERMEDIATE Continued Contractor continuing earthwork, preparing building pad.
11/15/2010 GRADING - INTERMEDIATE Continued Select construction began grading on Friday 11/12, removing vegetation.
11/08/2010 GRADING - INTERMEDIATE Continued Grading not started, utility locations in place, NPPO plants relocated, no grading activity.
11/25/2009 GRADING - INTERMEDIATE Continued Project not started, no activity
10/13/2009 GRADING - INTERMEDIATE Continued No Activity
05/11/2009 GRADING - INTERMEDIATE Not ready for Inspection No activity