| 09/15/2011 |
STORMWATER FOLLOW-UP INSP |
|
Approved |
Approved |
| 07/26/2011 |
STORMWATER FOLLOW-UP INSP |
|
Continued |
Still need to sweep a portion of praking lot . |
| 07/20/2011 |
STORMWATER FOLLOW-UP INSP |
|
Correction Required |
Remove trash from site sweep parking area. |
| 07/18/2011 |
STORMWATER FOLLOW-UP INSP |
|
Continued |
Parking lot need to be swept for dirt. |
| 07/06/2011 |
STORMWATER FOLLOW-UP INSP |
|
Continued |
Contractor needs to continue to monitor dirt on pavement onsite and clean up as needed to prevent track out. |
| 06/27/2011 |
STORMWATER FOLLOW-UP INSP |
|
Correction Required |
COntractor needs to sweep parking lot and install controls at off site inlets to storm drains |
| 06/08/2011 |
STORMWATER FOLLOW-UP INSP |
|
Correction Required |
Told contractor to provide protection and washout area for stucco contractor. |
| 05/05/2011 |
STORMWATER FOLLOW-UP INSP |
|
Correction Required |
Need controls around dirt stockpile on adjacent property that is being used as apart of this project. |
| 04/21/2011 |
STORMWATER FOLLOW-UP INSP |
|
Continued |
SWPPP controls in place and in good cond. |
| 03/22/2011 |
STORMWATER FOLLOW-UP INSP |
|
Correction Required |
New construction entrance in place all other controls in good cond. |
| 03/10/2011 |
STORMWATER FOLLOW-UP INSP |
|
Correction Required |
Construction entrance still not replaced, contractor said it will be done today, will issue NOV tomorrow if not complete. |
| 03/07/2011 |
STORMWATER FOLLOW-UP INSP |
|
Correction Required |
Construction entrance being replaced today, all other controls in good cond. |
| 02/28/2011 |
STORMWATER FOLLOW-UP INSP |
|
Correction Required |
Need to re-establish cionst. entrance rock |
| 02/11/2011 |
STORMWATER FOLLOW-UP INSP |
|
Correction Required |
Paving parking lot so minor track out onto Williams Blvd, contractor will sweep at end of the day. |
| 02/08/2011 |
STORMWATER FOLLOW-UP INSP |
|
Correction Required |
Minor trackout on Williams Blvd, needs to be swept up. |
| 01/26/2011 |
STORMWATER FOLLOW-UP INSP |
|
Continued |
Controls in place and in good shape. |
| 01/14/2011 |
STORMWATER FOLLOW-UP INSP |
|
Continued |
Storm controls in place and in good shape. |
| 01/05/2011 |
STORMWATER FOLLOW-UP INSP |
|
Continued |
Control in good shape. |
| 12/22/2010 |
STORMWATER FOLLOW-UP INSP |
|
Continued |
Storm controls in place and in good condition. |
| 12/20/2010 |
STORMWATER FOLLOW-UP INSP |
|
Continued |
Sotrm controls in good shape. |
| 12/17/2010 |
STORMWATER FOLLOW-UP INSP |
|
Continued |
Control in place and in good shape following last nights rain. |
| 12/09/2010 |
STORMWATER FOLLOW-UP INSP |
|
Continued |
Sotrm control are in good shape. |
| 11/29/2010 |
STORMWATER FOLLOW-UP INSP |
|
Continued |
stormcontrol look good, asked contractor to add straw waddel along south east entrance. |