Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T09BU00007

Parcel: 10712225A


Addresses:

2835 N STONE AV


Inspection Status: Approved

Inspection History: GRADING - INTERMEDIATE

Permit Number - T09BU00007

Inspection Description - GRADING - INTERMEDIATE

Inspection Status - Approved

Date Description Inspector Results Comments
08/30/2010 GRADING - INTERMEDIATE Approved
08/20/2010 GRADING - INTERMEDIATE Continued CONTRACTOR WILL LOOSE TWO PARKING SPOTS SHOWN ON THE APPROVED PLAN IN ORDER TO MEET THE THREE FOOT SET BACK BETWEEN THE PERIMETER WALL AND THE CURB - THE SITE WILL STILL MEET THE MINIMUM REQUIREMENT FOR PARKING.
CONTRACTOR MUST ENSURE THE SLOPE BELOW THE WALL IS PROPERLY PROTECTED FROM EROSION.

NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME
07/21/2010 GRADING - INTERMEDIATE Continued MET WITH SUPINTENDENT AND DISCUSSED THE RELEASE OF BLDG'S # 3 AND 4 ON SITE. CONSTRUCTION WILL BE COMPLETED NEXT WEEK AND LANDSCAPING SHOULD ALSO BE DONE. SOME SITE WORK REMAINS TO INCLUDE INSTALLATION OF A SWALE AROUND THE NW SIDE OF BLDG#3 AND THE INSTALLATION OF ROCK.
CONTRACTOR MUST ENSURE ANY REMAINING CONSTRUCTION ON SITE IS PHYSICALLY SEPARATED FROM PUBLIC ACCESS AND OCCUPANCY.
06/11/2010 GRADING - INTERMEDIATE Continued CONTRACTOR STILL WORKING ON BLDGS FOR PHASE TWO OF PROJECT. NO SITE WORK HAS BEEN COMPLETED FOR PHASE TWO. NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME
03/30/2010 GRADING - INTERMEDIATE Continued DEMO WORK ON SECOND PHASE OF PROJECT. 1 OF 4 BLDGS HAS BEEN TOTALLY DEMOLISHED, OTHER 3 BEING REFURBISHED. NO SITE WORK BEING DONE AT THIS TIME. NO STORM WATER CONCERNS AT THIS TIME.
02/11/2010 GRADING - INTERMEDIATE Continued PRELIMINARY INSPECTION FOR A RELEASE OF PART OF THE PROPERTY FOR OCCUPANCY, ENSURE REMAINING CONSTRUCTION AND PUBLIC ARE SEPARATED
02/10/2010 GRADING - INTERMEDIATE Continued PRIOR TO APPROVAL FROM ENGINEERING FOR A PARTIAL CERTIFICATE OF OCCUPANCY, ENSURE ANY REMAINING CONSTRUCTION IS PHYSICALLY SEPARATED FROM PUBLIC ACCESS AND THE OCCUPIED BLDGS UNTIL ALL WORK IS COMPLETED.
CONTRACTOR CHANGED THE CONCRETE VALLEY GUTTER OUTLET DIRECTION ALONG THE NE CORNER OF SITE - MUST PROVIDE STAMPED DRAWING SHOWING CHANGES MADE.
NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME.
01/08/2010 GRADING - INTERMEDIATE Continued MODIFICATIONS NEEDED TO CURB AND GUTTER DUE TO POWER POLE AND TIE DOWN - SE CORNER OF SITE.
NO STORM WATER CONCERNS
12/28/2009 GRADING - INTERMEDIATE Continued CONTRACTOR AND OWNER MAY WANT TO CHANGE HC PARKING LOCATION (WOULD REQ REVIEW FROM ZONING) DUE TO ELEVATION CHANGES TO BLDG FOUNDATION.

NO STORM WATER CONCERNS AT THIS TIME
12/10/2009 GRADING - INTERMEDIATE Continued MET W/ CONTRACTOR TO DISCUSS THE ADDITION OF MULITIPLE SCUPPERS TO SIDEWALKS AT AREAS OF DRAINAGE NEAR ROOF DRAINS - NO CONCERNS W/ CHANGES NEED STATEMENT FROM EOR

NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME
12/02/2009 GRADING - INTERMEDIATE Continued TOFFEL CONSTR, PEIRCE - 602-320-7427 AND GEORGE 623-203-2991

PROVIDE A DETAILED PHASING (TEMP) PLAN FOR TRANSFERRING CURRENT OCCUPANTS FROM EXISTING BLDGS TO NEWLY RENOVATED BLDGS SHOWING SAFE ACCESS, PARKING, TRASH SERVICE, AND DRAINAGE. ENSURE A PHYSICAL SEPARATION FROM CONSTRUCTION REMAINING AND THE PUBLIC.

NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME.
08/19/2009 GRADING - INTERMEDIATE Continued PRE-CON ACCOMPLISHED.
MET WITH CONTRACTOR, REVIEWED APPROVED SITE/GRADING PLAN. SOME DESCREPENCIES EXIST DUE TO LACK OF ROOM ( PAAL WIDTH...) ON SITE.
CONTRACTOR WIL COMPPLETE HALF THE SITE, THEN MOVE EXISTING OCCUPANT TO REMODLED SIDE AND COMPLETE THE SECOND HALF.
1) ALL CONSTRUCTION MUST BE SEPARATED FROM THE PUBLIC.
2) NO REQUIREMENT FOR SWPPP, HOWEVER TRACKING OF SOIL MUST BE SWEPT ROUTINELY AND ANY EXISTING STORM SEWER INLETS MUST BE PROTECTED.
3) CALL FOR INSPECTION FOR ANY CHANGES MADE TO THE APPROVED PLAN.