Inspection History Details
Inspection Status: Approved
Inspection History: ENGINEERING PRE-CONSTRUCTION
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/19/2009 | ENGINEERING PRE-CONSTRUCTION | Approved | PRE-CON ACCOMPLISHED. MET WITH CONTRACTOR, REVIEWED APPROVED SITE/GRADING PLAN. SOME DISCREPANCIES EXIST DUE TO LACK OF ROOM ( PAAL WIDTH...) ON SITE. CONTRACTOR WIL COMPPLETE HALF THE SITE, THEN MOVE EXISTING OCCUPANT TO REMODLED SIDE AND COMPLETE THE SECOND HALF. 1) ALL CONSTRUCTION MUST BE SEPARATED FROM THE PUBLIC. 2) NO REQUIREMENT FOR SWPPP, HOWEVER TRACKING OF SOIL MUST BE SWEPT ROUTINELY AND ANY EXISTING STORM SEWER INLETS MUST BE PROTECTED. 3) CALL FOR INSPECTION FOR ANY CHANGES MADE TO THE APPROVED PLAN. |