| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/29/2009 | SITE - SEWER | Approved | IVRS - Inspection :* | |
| 09/12/2008 | SITE - SEWER | Not ready for Inspection | IVRS - Inspection :* | |
| 09/11/2008 | SITE - SEWER | Partial Approval | IVRS - Inspection :* NEW 4" (#2) DIP BCS IN DIP FORM 8" OK STUB FOR NEW BUILDING |
|
| 09/10/2008 | SITE - SEWER | Partial Approval | IVRS - Inspection :* SDR35 STUB INTO NEW MANHOLE #3 TO BE TESTED AT LATER DATE |
|
| 09/09/2008 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 1. 8" SDR WITH TRACER WIRE AND APPROVED BEDDING STUB TO EXISTING SITE SEWER AT NEW MANHOLE |
|
| 09/08/2008 | SITE - SEWER | Partial Approval | IVRS - Inspection :* SITE SEWER 10' EAST OF EAST SIDE OF BUILD. |
|
| 09/05/2008 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 8" SDR 35 CONTINUES EAST APP. 40' WEST OF NEW MANHOLE #3 BASES POURED MANHOLE #2 * #4 PER INITIAL C-3.0 |
|
| 09/04/2008 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 8" SDR 35 FROM MANHOLE #4 TO #2 8" SDR 35 FROM MANHOLE #2 GOES EAST 83' TOWARD MANHOLE #3 -- BEDDING, LAYING, TRACER, SHADING |
|
| 09/03/2008 | SITE - SEWER | Partial Approval | IVRS - Inspection :* FROM NEW MANHOLE #3 PAGE C-30 APPROVED PLAN APP. 40' EAST TOWARD MANHOLE #2 BEDDING, LAYING, TRACER, SHADING |
|
| 08/29/2008 | SITE - SEWER | Not ready for Inspection | IVRS - Inspection :* NO CHANGE FROM 8/28/08 INSPECTION |
|
| 08/28/2008 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 8" SDR 35 FROM MANHOLE #4 TO #2 RE-ENGINEERED BEDDING, LAYING, TRACER, SHADING |
|
| 08/20/2008 | SITE - SEWER | Not ready for Inspection | IVRS - Inspection :* CONTRACTOR CANCELED |
|
| 08/19/2008 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 8" SDR FROM NEW MANHOLE #4 TO #2 8" SDR FROM MANHOLE #2 28' EAST, BEDDING, LAYING, TRACER WIRE, SHADING |