Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/03/2008 | PLUMBING - FINAL | Approved | IVRS - Inspection :* PROVIDE FULL SIZE DRAIN FOR T&P & BONDING OF BLD. GAP PIPING REINSPECTION OK |
|
| 04/01/2008 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection :* 1. PRIME THEN TAPE ALL FITTING UNDERGROUND TO 6" ABOVE GRADE 2. SUPPORT ALL PIPING AT CORRECT INTERVALS & SECURE IT 3. PROVIDE ROOF FLASHINGS AT BOTH PIPE PENETRATIONS THRU ROOF 4. PROVIDE AGA OR CSA APPROVED GAS VALVES AT ALL APPLIANCES 5. PROVIDE GRAVITY DRAIN TO DAYLIGHT OF APPROVED MATERIAL (COPPER OR CPVC) WITH 90 DEG. TERMINATION DOWN, 6"-24" FROM FINISH GRADE FOR WATER HEATER T&P DRAIN 6. PROVIDE BONDING OF BUILDING GAS PIPING AND GROUND ELECTRICAL SYSTEM RETEST ENTIRE SYSTEM 7. TEST INTO HEARTH OF FIREPLACE |
|
| 03/28/2008 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection :* CANCELED BY RUBEN |