Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T08PL00460

Parcel: 13329001A


Addresses:

545 N CAMINO SECO


Inspection Status: Approved

Inspection History: SITE - SEWER

Permit Number - T08PL00460

Inspection Description - SITE - SEWER

Inspection Status - Approved

Date Description Inspector Results Comments
07/15/2009 SITE - SEWER Approved IVRS - Inspection :*
10/20/2008 SITE - SEWER Partial Approval IVRS - Inspection :*
MANHOLE VACUUM TESTING #1 OK
#2 OK
#3 OK
#4 OK
#5 OK

NEED TO SEE WATERPROOF FRAME & COVER PER DETAIL 213.2
FOR MANHOLE #4 AND AUTHORIZATION TO DISCHARGE PCDEQ
10/16/2008 SITE - SEWER Partial Approval IVRS - Inspection :*
AIR TESTING - MANHOLE #1 TO #2 OK --- 8" SDR PIPING
#2 TO #3 OK
#3 TO #4 OK INCLUDING 4" HCS
#4 TO #5 OK
#5 TO EXISTING OK
10/03/2008 SITE - SEWER Partial Approval IVRS - Inspection :*
- PIPING BETWEEN MH #1 AND #2 OK
- MH BASES #1 & #2 BEING WORKED ON WILL REINSPECT AT TEST TIME
- SCHEDULE TEST TIME ONE DAY IN ADVANCE
10/02/2008 SITE - SEWER Partial Approval IVRS - Inspection :*
PIPING BETWEEN #3 & 2 OK
MH BASES 3 & 4 OK
09/29/2008 SITE - SEWER Partial Approval PIPING BETWEEN 3 & 4 OK
09/24/2008 SITE - SEWER Partial Approval IVRS - Inspection :*
1. PIPING BETWEEN #4 AND #5 APPEARS TO HAVE A SLIGHT CURVE. CHECK ALIGNMENT. OK TO COVER AFTER THIRD PARTY INSPECTION AND VERIFICATION
09/22/2008 SITE - SEWER Partial Approval IVRS - Inspection :*
FROM EXISTING MH TO NEW MANHOLE #5
PIPING OK
VERIFY GRADE
WILL AIR TEST LATER