Inspection History Details
Inspection Status: Partial Approval
Inspection History: SITE - SEWER
Permit Number - T08PL00397
Inspection Description - SITE - SEWER
Inspection Status - Partial Approval
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/01/2010 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 1) AIR TEST WITH NICH WESTPHAL FROM DOWL HCM FROM MANHOLE TO END OF ? CLEANOUT WITH (2) HCS LATERALS OK. NEED TO WITNESS ? |
|
05/27/2010 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 1) 8" D.I. WITH COATING CONTINUES TO 8" WYE BRANCH WITH 45 DEGREE PULL UP FOR FUTURE BLDG AND 8" SWEEP UP FOR END OF LINE CLEANOUT IN PLACE OF APPROVED MANHOLE PER PLAN. THIS WILL REQUIRE PCDEQ AND CITY OF TUCSON PLAN CHECK REVISION TO APPROVED PLAN PER 5/5/10 RFI #246 DOWEL HKM |
|
05/13/2010 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 1) AN ADDITIONAL 28' FEET OF PIPE HAS BEEN LAID |
|
05/12/2010 | SITE - SEWER | Not ready for Inspection | IVRS - Inspection :* | |
05/11/2010 | SITE - SEWER | Not ready for Inspection | IVRS - Inspection :* | |
04/28/2010 | SITE - SEWER | Not ready for Inspection | IVRS - Inspection :* 1) NO CHANGE |
|
04/27/2010 | SITE - SEWER | Not ready for Inspection | IVRS - Inspection :* 1) NO CHANGE |
|
04/26/2010 | SITE - SEWER | Not ready for Inspection | NO CHANGE | |
04/23/2010 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 1) NEXT LENGTH LAID, SUBJECT TO TEST AND VERIFICATION OF GRADE |
|
04/22/2010 | SITE - SEWER | Not ready for Inspection | IVRS - Inspection :* 1) NO CHANGE FROM LAST INSPECTION |
|
04/21/2010 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 1) TWO LENGTHS LAID PAST BCS CONNECTION, OK TO COVER SUBJECT TO VERIFICATION OF GRADE AND TEST |
|
04/20/2010 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 1) DIP TEE INSTALLED, NEXT LENGTH LAID |
|
04/19/2010 | SITE - SEWER | Not ready for Inspection | IVRS - Inspection :* 1) NO CHANGE TO PIPING INSTALL |
|
04/16/2010 | SITE - SEWER | Not ready for Inspection | IVRS - Inspection :* 1) NO CHANGE FROM 4/15/10 |
|
04/15/2010 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 1) 8" SP-2000 DUCTILE APP 80' FROM PUBLIC MANHOLE UP STREAM 2) 3RD PARTY INSPECTION IS REQUIRED ON THIS PROJECT FOR PCDEQ AUTHORIZATION TO DISCHARGE IN ORDER TO TIE IN BLDG SEWERS |
|
04/14/2010 | SITE - SEWER | Not ready for Inspection | IVRS - Inspection :* 1) NO CHANGE FROM 4/13/10 |
|
04/13/2010 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 1) 8" SP-2000 PVC TILE 40' EAST OF PUBLIC MANHOLE |
|
04/12/2010 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 1) TRENCHING 2) FIRST STICK OF D.I.P. INSTALLED |
|
04/08/2010 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 1) GRADING IN PREPARATION TO START TRENCHING |