Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/05/2008 | PLUMBING - FINAL | Approved | IVRS - Inspection :* SEE NOTE #3 FROM 2/1/08 COMPLETE INSTALL OF FURNACE WITH CORRECT VENTING FOR BOTH WATER HEATER AND FURNACE. COMPLETE ITEM #5 FROM 2/1/08 |
|
| 02/01/2008 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection :* 1. COMPLETE GAS PIPING IN ITS ENTIRETY WITH APPROVED GAS SHUT OFF VALVES AND TEST SYSTEM AT MINIMUM 10 PSI FOR 15 MINUTES WITH NO LOSS OF PRESSURE AT TIME OF INSPECTION. 2. SUPPORT GAS PIPING 3. PROVIDE CORRECT VENTING FOR FURNACE/WATER HEATER 4. PROVIDE TEMPERATURE & PRESSURE RELIEF DRAIN PIPING FOR WATER HEATER 5. PROVIDE BONDING OF BUILDING GAS SYSTEM |