Inspection History Details
Inspection Status: Approved
Inspection History: INSP - FULL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/03/2009 | INSP - FULL | Approved | ITEMS #-S 1-3-4 CORRECTED. ITEM #2 IS BEING TRANSFEERED TO A NEW FRO NUMBER TO GO WITH A NEW DATED SPRINKLER REPORT | |
| 10/28/2008 | INSP - FULL | Correction Required | DURING THE ANNUAL SPRINKLER SYSTEM INSPECTION THE FOLLOWINF DEFICIENCIES WERE FOUND AND SHALL BE CORRECTED WITH IN 30 DAYS. A COPY OF THE REPAIR MANIFEST SHALL BE FORWARDED TO THIS OFFICE. 1) THE SPRINKLER RISER IS DUE FOR THE 5 YEAR INTERNAL INSPECTION 2) A SPARE HEAD BOX WITH THE CORRECT COMPLIMENT OF SPARE HEADS SHALL BE PROVIDED AT THE RISER. 3) A KEY SHALL BE PROVIDED FOR THE LOCKED CAKE AT THE SPRINKLER RISER SO THAT THE REQUIRED FLOW TEST CAN BE PERFORMED. 4) THE VALVE FOR THE WATER MOTOR GONG SHALL BE IN THE CORRECT POSITION. |