Permit: T08EL01262

Parcel: 12605065A


Addresses:

4202 E SPEEDWAY BL

Inspection Status: Approved

Inspection History: ELECTRIC - FINAL

Date Description Inspector Results Comments
08/28/2009 ELECTRIC - FINAL Approved CORRECTIONS MADE. CIRCUITS TESTED OK.
07/23/2008 ELECTRIC - FINAL Partial Approval IVRS - Inspection :*
07/17/2008 ELECTRIC - FINAL Denied IVRS - Inspection :
See detailed listing on site.| 999*
1. GROUND RODS TO BE MIN. 6' APART
2. NEED PANEL DIRECTORY
3. OPEN ONE SIDE OF NEW WALLS TO INSPECT ALL NEW ELECTRIC
4. REPLACE ALL PAINTED OVER DEVICES (RECEPTACLES & SWITCHES)
5. HAVE LADDER FOR ROOF INSPECTION
07/09/2008 ELECTRIC - FINAL Denied IVRS - Inspection :
See detailed listing on site.| 999*
1. ALL NEW ELECTRIC WORK WILL REQUIRE PLANS & PERMIT
POWER WILL NOT BE TURNED ON UNTIL THIS IS DONE
2. REPLACE ALL PAINTED OVER DEVICES
3. INSTALL DEAD FRONT ON PANEL
4. SPLIT BREAKERS IN PANEL NOT FOR USE IN CTL PANEL.
THESE BREAKERS ARE FOR REPLACEMENT USE ONLY
5. GROUNDS & NEUTRALS TO BE SEPARATE @ SUB-PANELS
6. PANEL APPEARS TO BE NEW WILL REQUIRE PLAN & PERMIT
7. BATHROOM RECEPT TO BE GFI PROTECTED
8. NEED PANEL DIRECTORIES
9. GROUNDING ELECTRODE SYSTEM CUT & STOLEN INSTALL NEW GROUNDING ELECTRODE SYSTEM. BOND GAS & WATER PIPING
10. HAVE QUALIFIED ELECTRICAL CONTRACTOR GO THROUGH ENTIRE JOB ONCE PLANS & PERMITS OBTAINED
11. PROVIDE LADDER FOR ROOF ACCESS