Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - ROUGH, SOIL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/29/2009 | PLUMBING - ROUGH, SOIL | Approved | IVRS - Inspection :* | |
| 04/14/2009 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 1) ALL UNDERGROUND WATER TEST ONLY OK PENDING RED LINE ON SITE |
|
| 04/13/2009 | PLUMBING - ROUGH, SOIL | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1. PROVIDE FLOOR DRAIN WITH CORRECT CONNECTION AND CORRECT SIZE PER PLAN, THERE SHALL BE NO LEDGE OR RESTRICTION IN FLOW ON TAILPIECE 2. INSTALL PER APPROVED PLAN OR PROVIDE REDLINES ON SITE FOR CHANGES YOU HAVE MADE 3. A 3" DRAIN WOULD BE REQUIRED TO WET VENT THE FLOOR DRAIN WITH THE URINAL 4. NOTE: PLASTIC PIPING WILL NOT BE ALLOWED IN A RETURN AIR PLENUM UNLESS IT CAN MEET THE CORRECT SMOKE AND FLAME RATING |
|
| 03/10/2009 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* |