Inspection History Details
Inspection Status: Approved
Inspection History: ELECTRIC - PROGRESS
Permit Number - T08CM03574
Inspection Description - ELECTRIC - PROGRESS
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/10/2010 | ELECTRIC - PROGRESS | Approved | ||
10/09/2009 | ELECTRIC - PROGRESS | Partial Approval | IVRS - Inspection :* | |
10/01/2009 | ELECTRIC - PROGRESS | Partial Approval | IVRS - Inspection :* | |
09/04/2009 | ELECTRIC - PROGRESS | Partial Approval | IVRS - Inspection :* 1) RECEIVING AREA P1.1 CIRCUIT FOR BELL, PC2.3 CIRCUIT FOR ISOLATED OUTLETS, H2 EM LIGHTING AND DOOR IDF BOX FOR COMMUNICATIONS 2) H2.1.3.5 FOR ALL LIGHTING AND SUMP PUMP RACEWAY OK |
|
09/02/2009 | ELECTRIC - PROGRESS | Partial Approval | IVRS - Inspection :* 1) REMOTE DEFROST PANEL ON TOP OF FREEZER 2) CONDUITS FROM RDP TO EXISTING J-BOXES FOR BRANCH CIRCUITS OK 3) CONDUITS FOR CONTROL CIRCUITS ALL NEW OK |
|
09/01/2009 | ELECTRIC - PROGRESS | Partial Approval | IVRS - Inspection :* 1) P.31-P.32 PANELS FEED ANTI-SWEAT MISER, AND TRANS FEED PANEL 2) P.1 BONDED AND GROUND 3 POLE 30 AMP, H7-15 AMP PANEL, R.D.P. SMART BREAKERS FOR FREEZER LIGHTS 480V 3) USE DUCT SEAL AND SILICONE FOR PENETRATIONS |
|
08/28/2009 | ELECTRIC - PROGRESS | Partial Approval | IVRS - Inspection :* 1) 1 1/4 IN 1 1/4 OUT OF POLE BASE PVC IN TRENCH BEHIND BLDG, MEZZANINE 600 AMP ? AND BONDED OK |
|
08/26/2009 | ELECTRIC - PROGRESS | Partial Approval | IVRS - Inspection :* 1) SWITCH GEAR FOR COMPRESSORS OK 2) MEZZLINE SUB PANELS OK 3) H-8" 4 200 AMP BUCKET 4-4/0 #6 GROUND 600 AMP #3 GROUND |
|
08/19/2009 | ELECTRIC - PROGRESS | Partial Approval | IVRS - Inspection :* 1) FIRE PUMP DISCONNECT-OK 2) FIRE PUMP CONTROLLER-OK |
|
08/17/2009 | ELECTRIC - PROGRESS | Partial Approval | IVRS - Inspection :* 1) RACK A AND RACK B DISCONNECTS AND PANELS OK 2) TRANSFORMER AND #2 LIGHTING PANEL OK |
|
07/24/2009 | ELECTRIC - PROGRESS | Partial Approval | IVRS - Inspection :* 1) LOW VOLTAGE CLEANED UP AND STRAPPED 2) DAIRY COOLER FAN COILS AND DEFROST NEED TO BE MOVED, J-BOX FOR PROPER CLEARANCE 3) TRANSFORMER GROUNDING AND SWITCH GEAR-OK 4) NEED STAND FOR COMPRESSOR DISCONNECTS AND PIPES |
|
07/23/2009 | ELECTRIC - PROGRESS | Partial Approval | IVRS - Inspection :* 1) NEED BOND BUSHING AT TRANSFORMER |
|
07/17/2009 | ELECTRIC - PROGRESS | Partial Approval | IVRS - Inspection :* | |
07/15/2009 | ELECTRIC - PROGRESS | Partial Approval | IVRS - Inspection :* 1) MAINTENANCE SOUTH WALL-OK |