Permit: T08CM03438

Parcel: 117200270


Addresses:

260 S CHURCH AV 01

Inspection Status: Approved

Inspection History: MECHANICAL - HYDRONIC PIPING

Date Description Inspector Results Comments
08/17/2009 MECHANICAL - HYDRONIC PIPING Approved IVRS - Inspection :*
05/01/2009 MECHANICAL - HYDRONIC PIPING Partial Approval IVRS - Inspection :*
PRESS HYDRO TEST FROM EXISTING TIE IN TO FIRE CENTRAL OK - OK TO COMPLETE INSULATION
01/08/2009 MECHANICAL - HYDRONIC PIPING Partial Approval IVRS - Inspection :*
12/15/2008 MECHANICAL - HYDRONIC PIPING Partial Approval IVRS - Inspection :*
12/05/2008 MECHANICAL - HYDRONIC PIPING Partial Approval IVRS - Inspection :*
NORTH PIPING AT CUSHING ST. PARKING LOT TO EL PASO ST
PRESS. TEST OK
12/02/2008 MECHANICAL - HYDRONIC PIPING Partial Approval IVRS - Inspection :*
SOUTH PIPING AT CUSHING ST. PARKING LOT TO EL PASO OK
11/25/2008 MECHANICAL - HYDRONIC PIPING Partial Approval IVRS - Inspection :*
HYDRONIC UNDERGROUND CROSSING CUSHING ST TO EAST END OF PARKING LOT -- OK TO COVER -- TEST OK