Inspection Status: Approved
Inspection History: PLUMBING - ROUGH, SOIL
Permit Number - T08CM03250
Inspection Description - PLUMBING - ROUGH, SOIL
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/12/2009 | PLUMBING - ROUGH, SOIL | Approved | IVRS - Inspection :* | |
02/03/2009 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* OK TO CONTINUE POURING |
|
01/27/2009 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* PARTIAL UNDERGROUND AT MECHANICAL ROOM OK TO COVER TO OUTSIDE ROOM ONLY |
|
01/23/2009 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* N/H UNDERGROUND AT #137 & #139 AND FOR COOLING TOWER WHICH IS INSTALLED PER REDLINES -- OK TO COVER |
|
01/22/2009 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :* | |
01/20/2009 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 1. TOILET ROOMS #128, #129, #147, #148 AND MAIN LINE TO EXTERIOR WALL OK. I NEED TO SEE CONTINUATION FOR #139, #137 OK TO COVER 2. PRESLAB FOR #116, 120, 124 RESTROOM 104 AND 105 OK FOR CONCRETE |
|
01/08/2009 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 1. RESTROOM 104 AND ROOM 105 TO CONNECTION AT MAIN ALREADY INSPECTED BY B.BENEDON -- OK TO COVER |
|
12/24/2008 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* SOIL PIPING PER REDLINES FROM RM. 116 THROUGH TWO-WAY CO AND INCLUDING STAFF TRS 120.21 AND 124 |
|
12/23/2008 | PLUMBING - ROUGH, SOIL | Denied | IVRS - Inspection : See detailed listing on site.| 999* POST ADDRESS SLOPE IN TWO PLACES |