Permit: T08CM03250

Parcel: 10601247B


Addresses:

125 E PRINCE RD

Inspection Status: Approved

Inspection History: REINFORCED MASONRY PRE-GROUT

Date Description Inspector Results Comments
08/19/2009 REINFORCED MASONRY PRE-GROUT Approved IVRS - Inspection :*
04/01/2009 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
TOP OUT WEST SIDE
03/30/2009 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
85' WEST SCREEN WALL 1ST LIFT
03/27/2009 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
24' G.L. 3/H-M; 3.5/H-M
03/25/2009 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
TOP OUT SOUTH WALL; 20' MECH. ROOM 16' G.L. K/3-5
03/23/2009 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
24'-28' SOUTH WALL
03/20/2009 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
TOP OUT RAKE WALL G.L. 5/H-K, 20' LIFT G.L. H-K/2
03/17/2009 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
1. NORTH CLASSROOM WALL LAST 4' TO TOPOUT
2. EAST STAIRWELL TO 28'
3. 5 SOUTH PIERS TO 24' TOP OUT
4. TO BE SPECIAL INSPECTED BY BRODERICK
03/16/2009 REINFORCED MASONRY PRE-GROUT Partial Approval CMU WALL @ LINE E.5/5 - K-5/6 @ 20'; LINES E.5/5-3.5
E.5/3.5-4/3.5 @ 16; MECHANICAL ROOM LINES H3.5-4.5;
K3.5/4.5 @ 16 --- OK TO GROUT PROGRESS AREAS
03/13/2009 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
28' NORTH WALL AND WEST STAIRWAY
03/12/2009 REINFORCED MASONRY PRE-GROUT Partial Approval SOUTH WALL @ 24'
03/11/2009 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
G.L. 17.8/E-G TOP OUT
G.L. 24' 15.6/D-G
03/10/2009 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
20' LIFT SOUTHWALL; 24' LIFT ELEVATOR SHAFT
03/09/2009 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
21'4" NORTH WALL; 16' AT MECH. ROOM
03/06/2009 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
G.L. - H-K-15.5-16.5 20'
G.L. - 5.3/H-J 20'
G.L. - 5/D.5-Z-5 16'
G.L. - 1/D-H 16'
03/04/2009 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
20' LIFT NORTH WALL AND ELEVATOR SHAFT
16' LIFT SOUTH WALL
03/02/2009 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
G.L. 20' 18-18.5/H-H.5
G.L. 4-5/H-I 12'
02/27/2009 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
16' ELEVATOR SHAFT AND CIRCULAR WINDOWS WALL
02/26/2009 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
16' ELEVATOR WALL, SOUTH RAKE WALL TOP OUT
16' NORTH WALL WITH WINGS
02/25/2009 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
16' LIFT AT CIRCLE WINDOW; 12' SOUTH WALL AND COLUMNS
02/24/2009 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
17'4" SOUTH RAKE WALL
02/20/2009 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
12' LIFT NORTH WALL G.L. 5 - L - H, G.L. 6.5 - 18 - 19.5
02/18/2009 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
RAKE WALL AT ADMIN. BUILDING; 1ST LIFT MECH. YARD
2ND LIFT RECEPTION HALLWAY
02/13/2009 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
NORTH AND SOUTH PILLARS
02/12/2009 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
1) TOP OUT AT ADMIN BLDG WEST, NORTH AND EAST WALLS 4TH LIFT ON SOUTH WALL, 3RD LIFT ON SOUTH PILARS
02/11/2009 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
NORTH WALL 4'-6'; 2ND LIFT STAIRWELL
02/06/2009 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
12' AD RUN BLD; 1ST LIFT AREA 1-5;
8' FRONT ENTRY AREA 18/F
02/03/2009 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
1ST LIFT CLASSROOM
01/29/2009 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
2ND LIFT ADMIN. BUILDING EAST,
NORTH AND HALF OF WEST WALLS
01/27/2009 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
1ST LIFT ADMIN. BUILDING
01/13/2009 REINFORCED MASONRY PRE-GROUT Not ready for Inspection IVRS - Inspection :*