Inspection History Details
Inspection Status: Approved
Inspection History: ENGINEERING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/23/2010 | ENGINEERING - FINAL | Approved | CLOSED PER CRAIG E-MAIL 4-22-10 | |
| 12/15/2009 | ENGINEERING - FINAL | Partial Approval | Complete items1,3,5,7,10,11,12,13 from the 12/08 punch list. Relocate 2 downspouts at rear of building so that they do not dump directly onto the sidewalks. |
|
| 12/08/2009 | ENGINEERING - FINAL | Denied | OK for Stocking and training, if a construction area in the parking lot is established to separate construction form public. Complete the following prior to C of O. 1) Trash enclosers do not match approved plan, const. per plan or revise plan. Min. opening 10ft. 2) Stripe access crossings at all PAAL's. 3) Provide 4ft S/W scuppers per plan or revise. 4) Stripe loading zones per plan. 5) Provide post barricades per plan. 6) Install 5ft sidewalk along east edge of parking per plan or revise. 7) Provide class I & II bike parking per plan. 8) Revise plan for changes made at main entry to bldg. 9) Provide H.C. signs per plan 10) Place rip rap per detail J sht. 3 or revise. 11) Place water harvest areas per plan or revise. 12) Remove all construction debris. 13) Clean existing detention basins, remove silt and debris. 14) Call for re-inspection. |
|
| 11/17/2009 | ENGINEERING - FINAL | Denied | Call for final grading inspection prior to C of O final. 1)Complete all items on approved site plan. 2) Finish all sidewalks and ramps 3) remove all construction debris 4) stabilize all disturbed areas 5) clean silt from all offsite basins and asphalt drives 6) call for re-inspection. |