Inspection History Details
Inspection Status: Approved
Inspection History: MECHANICAL - PROGRESS
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/07/2009 | MECHANICAL - PROGRESS | Approved | IVRS - Inspection :* 1) N.E., 2 N.E., 3 N.E. OK 2) N.W., 2 N.W., 1 N.W. OK 3) OK TO COVER DUCT CHASE N. OF BLDG ( X2) |
|
| 08/04/2009 | MECHANICAL - PROGRESS | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1) NEXT FAILED INSPECTION WILL RESULT IN A REFEE |
|
| 07/31/2009 | MECHANICAL - PROGRESS | Not ready for Inspection | IVRS - Inspection :* | |
| 06/25/2009 | MECHANICAL - PROGRESS | Partial Approval | IVRS - Inspection :* | |
| 06/23/2009 | MECHANICAL - PROGRESS | Partial Approval | IVRS - Inspection :* 1. NORTHWEST CORNER - DO NOT COVER CHASE 2. NORTHEAST CORNER - DO NOT COVER CHASE |
|
| 06/08/2009 | MECHANICAL - PROGRESS | Not ready for Inspection | IVRS - Inspection :* 1. PROVIDE APPROVED ACCESS TO UNITS 2. INSULATE EXHAUST PIPING AS REQUIRED 3. INSTALL FIRE DAMPERS IN APPROVED MANNER 4. PROVIDE SUBMITTALS ON FIRE DAMPERS BEING USED |
|
| 05/27/2009 | MECHANICAL - PROGRESS | Partial Approval | IVRS - Inspection :* | |
| 05/26/2009 | MECHANICAL - PROGRESS | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1. ALL DUCT TO BE SEALED WITH MASTIC, TAPE NOT ACCEPTABLE 2. ALL DUCT JOINTS TO BE MECHANICALLY FASTENED MIN. 3 SCREWS PER JOINT 3. PROVIDE PROPER FIRE RATING AT CHASES 4. VERIFY FIRE DAMPERS AT CHASE TO ATTIC SPACE |