Permit: T08CM02601

Parcel: 14042075D


Addresses:

2705 E EXECUTIVE DR

Inspection Status: Approved

Inspection History: PLUMBING - ROUGH, SOIL

Date Description Inspector Results Comments
12/09/2009 PLUMBING - ROUGH, SOIL Approved IVRS - Inspection :*
12/08/2009 PLUMBING - ROUGH, SOIL Not ready for Inspection IVRS - Inspection :*
1) PROVIDE APPROVED PLANS FOR ALL CHANGES
2) PROVIDE SUPPORT AND INSULATION IN WATER HEATER ROOM FOR RETURN HOT WATER
3) COMPLETE INSTALL OF ALL SODA, COFFEE, ETC...
11/09/2009 PLUMBING - ROUGH, SOIL Not ready for Inspection IVRS - Inspection :*
1) 03005, 03015,03035-PROVIDE CITY APPROVED PLANS AND RED LINES ON SITE
2) PROVIDE SIGNAGE AT MAIN SERVICE PANEL OF NON-METALLIC NOT BONDED WATER PIPING ON THIS PROJECT
3) 3RD LEVEL PLUMBING FIXTURES FOR ? ROOMS OK
03/27/2009 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*
UNDERGROUND TEST TO CLEANOUTS OK
03/25/2009 PLUMBING - ROUGH, SOIL Not ready for Inspection IVRS - Inspection :*
03/09/2009 PLUMBING - ROUGH, SOIL Not ready for Inspection IVRS - Inspection :*
1. STUB UP 5' FROM LOT LINE TO BUILDING TEST OK (ONLY)
03/06/2009 PLUMBING - ROUGH, SOIL Not ready for Inspection IVRS - Inspection :*
02/20/2009 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*
1. PROVIDE GREASE TRAP PER APPROVED PLANS
2. PROVIDE APPROVAL FOR ALL CHANGES
3. ROUGH SOIL FOR ROOMS TEST OK
02/19/2009 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*
PER HIGHLIGHT ON PAGE P-2.1 TEST OK
PER REDLINES TO BE APPROVED
02/18/2009 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*
1. PRE-SLAB FOR PAGE A 1.01 AREA "B" OK FOR CONCRETE
2. ROUGH/SOIL FOR AREA "A" UP TO CONFERENCE ROOM ON PAGE 1.01A OK TO COVER
INSTALLED PER REDLINES ON FRANK'S APPROVED PLAN
02/13/2009 PLUMBING - ROUGH, SOIL Not ready for Inspection IVRS - Inspection :*
02/06/2009 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*
ON PAGE A-1.01B AREA "B" ROUGH SOIL TEST OK
PER REDLINE ON PAGE P-2.0 TO BE APPROVED AT LATER DATE
02/05/2009 PLUMBING - ROUGH, SOIL Not ready for Inspection IVRS - Inspection :*
02/04/2009 PLUMBING - ROUGH, SOIL Not ready for Inspection IVRS - Inspection :*
02/03/2009 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*
1. PROVIDE REDLINE ON APPROVED SET OF PLANS
2. COMPLETE WEST SIDE ROUGH SOIL PER REDLINE AND CALL BACK
3. REDLINES TO BE APPROVED BY ENGINEER WITH STAMP
02/02/2009 PLUMBING - ROUGH, SOIL Not ready for Inspection IVRS - Inspection :*
INSTALL PER APPROVED PLANS

FRANK GARCIA @ 227-0223
01/23/2009 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*
01/22/2009 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*
8" FROM MANHOLE WITH PLUG IN MANHOLE 10' TO BUILDING