Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Approved
Inspection History: BUILDING PRE-SLAB
Permit Number - T08CM02395
Inspection Description - BUILDING PRE-SLAB
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/18/2010 | BUILDING PRE-SLAB | Approved | ||
04/08/2010 | BUILDING PRE-SLAB | Partial Approval | NORTH END OF ROOF OVER TO MECH ROOM. | |
03/15/2010 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* 1) MAIN LIFT PAD OK |
|
03/09/2010 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* 1) BOOSTER PUMP B.1 LEVEL |
|
02/08/2010 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* 1) NORTH PORTION OF 5TH FLOOR-G.L. 5/B-E-OK TO POUR PROGESS AREA |
|
01/11/2010 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* 1) 6TH FLOOR GL A/J |
|
01/05/2010 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* 1) 5TH FLOOR A/J |
|
12/14/2009 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* STAIRWAY TREADS |
|
12/03/2009 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* N1/2 4TH LEVEL OK TO PLACE WHEN SPECIAL INSPECTION CONFIRMS NOTE 1. EXCESSIVE FOAM FILL@NE BALCONY & AROUND SEVERAL COLUMNS, PLEASE TRIM BACK TO PAN |
|
12/02/2009 | BUILDING PRE-SLAB | Partial Approval | ||
12/01/2009 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* 1/2 3RD FLOOR OK |
|
11/24/2009 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* 1) 2ND FLOOR OK |
|
11/12/2009 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* 1) 4TH FLOOR GL J-F |
|
11/09/2009 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* 1) GL J-F 3RD FLOOR |
|
11/03/2009 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* 1) GL J-F 2ND FLOOR |
|
11/02/2009 | BUILDING PRE-SLAB | Not ready for Inspection | IVRS - Inspection :* 1) WORK INCOMPLETE |