Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T08CM02391

Parcel: 12701005D


Addresses:

5151 E BROADWAY BL


Inspection Status: Approved

Inspection History: PLUMBING - INTERMEDIATE

Permit Number - T08CM02391

Inspection Description - PLUMBING - INTERMEDIATE

Inspection Status - Approved

Date Description Inspector Results Comments
10/29/2009 PLUMBING - INTERMEDIATE Approved IVRS - Inspection :*
09/24/2009 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
1) #137,134,136, ABS THRU ? FOR TEST OK
2) WATER PIPING TIE TO ? #137 AND 134 OK (ONLY)
3) TI FOR TUCSON COLLEGE
09/23/2009 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
1) PRE-SLAB IN ROOM #112 AND 112 OK (ONLY)
2) INSULATION IN #131, 132 & 133
09/22/2009 PLUMBING - INTERMEDIATE Partial Approval 1) PIPING PER RED LINE FOR WATER IN ROOMS #131, 133 AND 132 (TUCSON COLLEGE-TI)
09/21/2009 PLUMBING - INTERMEDIATE Partial Approval 1) VENTS THRU ROOF TEST OK IN ROOMS #132,133,141,142,126,163,156 AND 160 (VENTS ONLY)
2) PROVIDE APPROVED PLANS ON SITE
3) INSPECTION FOR TI FOR TUCSON COLLEGE
4) ROUGH SOIL OR SOUTHWEST SIDE OF BLDG FOR TIE IN PER RED LINE
5) NO CHECK ON SITE-$150.00 TO BE PAID FROM BARKER AND MORRISEY ACCOUNT FOR REQUESTED AFTER HOURS INSPECTIONS
09/18/2009 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
1) TRM'S, DF, MS 151-153 PIPING AND INSULATION OK TO COVER
09/16/2009 PLUMBING - INTERMEDIATE Not ready for Inspection IVRS - Inspection :*
09/15/2009 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
1) #138-138B. 139-139B, 136. 126 HALLWAY OFF #147 WATER ? AND 142 AND 141 ABS (INSPECTION FOR TUCSON COLLEGE-TI)
09/14/2009 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
1) WATER PIPING IN WALLS (ONLY) FOR P-6'S IN ROOMS 138,138A,138B AND 139, 139B, 139A AND ROOM 141 P-4 & P7 AND ROOM 142 P.5 WATER PIPING IN WALLS (ONLY)
2) THIS INSPECTION FOR TUCSON COLLEGE T.I. (NO APPROVED PLAN ON SITE) PIPING INSTALLED PER RE LINE
09/11/2009 PLUMBING - INTERMEDIATE Partial Approval 1) IN WALLS AT ROOMS 160, 156, 163, 149, 141 AND 142 WITH 1/2 ARMORFLEX AND 100 PSI TEST OK TO COVER SUBJECT TO APPROVED PLAN WITH MATERIAL SPECS
09/10/2009 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
1) PRE-SLAB IN AREAS INSPECTED ON 9/8/09 OK
09/08/2009 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
1) ROOM 133,132,138S,139S AND 131 PIPING WITH TEST TO ABOVE CEILING
2) PRE-SLAB OF PREVIOUSLY INSP AREAS OK
09/04/2009 PLUMBING - INTERMEDIATE Not ready for Inspection ROUGH SOIL IN ROOM #137,134,136,160,163 AND 156 INSTALLED PER RED LINES. PER LEE RAY HAVE RED LINES P-1.1 AND P-1.0 ON SITE TO MATCH CITY OF TUCSON APPROVED PLAN
2) TEST THRU CLEANOUTS
3) COVER AT OWN RISK
4) NO CHECK ON SITE. PER LEE RAY HANLY TO BE PAID FROM BAKER/MORRISSEY (APA ACCOUNT) MIN 2 HR INSPECTION FOR $150.00
09/04/2009 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
1) ROOM #141 AND 142 SOIL PIPING AND IN WALLS WITH TEST TO ABOVE CEILING
2) DEMO AT COL LINES 4/5
3) RECALL FOR PRE-SLAB INSPECTIONS
4) ALSO RECALL INSPECTION AS SOON AS PLANS AND PERMITS ARE IN ORDER
09/02/2009 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
1) P-6 ROOM 160 WITH TEST TO ABOVE CEILING OK
2) P-4 ROOM 149 WITH TEST TO ABOVE CEILING OK
3) INSTALL WRAPS, RED LINE CHANGE
4) INSTALL PERM CAPS ON IN WALL DEMO
5) PROVIDE CITY APPROVED PLANS