Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - GAS PRESSURE TEST
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/10/2012 | PLUMBING - GAS PRESSURE TEST | Approved | IVRS - Inspection :* | |
| 09/21/2011 | PLUMBING - GAS PRESSURE TEST | Not ready for Inspection | IVRS - Inspection :* 1) COMPLETE PIPING INSTALLATION TO ROOF TOP UNIT IF REQUIRED THEN TEST, NO UNIT AT THIS TIME 2) HAVE NEW ROOF TOP UNIT ADDED TO THIS PERMIT AND HAVE INSPECTED |
|
| 04/27/2011 | PLUMBING - GAS PRESSURE TEST | Denied | IVRS - Inspection : See detailed listing on site.| 999* TEST GRADE TO BE FUNCTIONAL AND BE IN 1/10 POUND INCREMENTS |
|
| 03/19/2010 | PLUMBING - GAS PRESSURE TEST | Not ready for Inspection | IVRS - Inspection :* 1) HAVE LADDER ON SITE FOR ROOF INSPECTION 2) PLUMBING INTERMEDIATE BEFORE DRY WALLING TO SEE PLUMBING IN WALLS FOR INSPECTION |
|
| 02/05/2010 | PLUMBING - GAS PRESSURE TEST | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1) HAVE PLANS ON SITE, PROVIDE ACCESS TO ALL GAS APPLIANCES, PROVIDE UNIT # ON UNIT 2) HAVE TEST IN PLACE WITH CORRECT TEST GAUGE |