Inspection Status: Approved
Inspection History: PLUMBING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/30/2009 | PLUMBING - FINAL | Approved | IVRS - Inspection :* 1) PLUMBING FINAL OK |
|
| 06/26/2009 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection :* | |
| 06/23/2009 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection :* 1. SEE GENERAL NOTES ON P-2 TRIM NOT INSTALLED PER PLAN 2. SEE WATER HEATER DETAIL NOT INSTALLED PER PLAN 3. PROVIDE LETTER FROM ARCHITECT ALLOWING ARMAFLEX |
|
| 06/12/2009 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection :* 1. MULLER 3" OFFSET FLANGE IS NOT LISTED TO BE INSTALLED INSIDE 4" PIPE 2. BACKFLOW PROTECTION INSTALLED IS NOT PER PLAN 3. EQUIPMENT IS NOT ON SITE, BACKFLOW PROTECTION MAY BE REQUIRED AT BEVERAGE EQUIPMENT. LIST NOT COMPLETE |
|
| 06/09/2009 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection :* 1. PLEASE CALL IN AND HAVE APPROVED ALL REQUIRED INSPECTIONS PRIOR TO CALLING FINAL 2. WATER CLOSETS SET BEFORE FLANGE INSPECTION 3. PROVIDE STERILIZATION REPORT PROVIDE CLEAN BACTERIA REPORT THIS IS NOT A PUNCH LIST - NOT READY FOR FINAL INSPECTION |