Inspection History Details
Inspection Status: Approved
Inspection History: FRAMING
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/14/2009 | FRAMING | Approved | IVRS - Inspection :* | |
| 02/19/2009 | FRAMING | Partial Approval | IVRS - Inspection :* CORRIDOR OK CAULK PENETRATION |
|
| 01/09/2009 | FRAMING | Partial Approval | IVRS - Inspection :* 2ND FLOOR 2 @ BOX BEAMS AS PER RFI #ASI 2-0 (1/5/09) HARD LID IN ROOM #200; BOX BEAM @ 1ST FLOOR AS PER PLANS -- OK TO COVER |
|
| 12/16/2008 | FRAMING | Partial Approval | IVRS - Inspection :* ELEVATOR SHAFT OK |
|
| 09/09/2008 | FRAMING | Not ready for Inspection | IVRS - Inspection :* CONTRACTOR CANCELED |
|
| 09/04/2008 | FRAMING | Not ready for Inspection | IVRS - Inspection :* SEE DETAIL A5.0/13 |