Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - GAS PRESS TEST FNL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/27/2009 | PLUMBING - GAS PRESS TEST FNL | Approved | IVRS - Inspection :* NO ACCESS TO ROOF STAIRS TAPED OFF USED THE ELEVATOR CONTRACTOR SAID CORRECTIONS MADE PER NOTES ON 3/25/09 |
|
| 03/26/2009 | PLUMBING - GAS PRESS TEST FNL | Partial Approval | IVRS - Inspection :* PROVIDE SOAP TEST AT FINAL RELOCATE CLAMP ON PANEL STILL NEED 2" CLEARANCE ABOVE ROOF AT SEDIMENT TRAP OK TO PAINT PER PLAN SPEC. |
|
| 03/25/2009 | PLUMBING - GAS PRESS TEST FNL | Denied | IVRS - Inspection : See detailed listing on site.| 999* PROVIDE FULL SIZE PIPING TO INLET LOCATION ALSO, KEEP SEDIMENT TRAP 2" ABV ROOF |
|
| 02/19/2009 | PLUMBING - GAS PRESS TEST FNL | Partial Approval | IVRS - Inspection :* OK TO COVER ALL AREAS GAS PRESSURE TEST OK |
|
| 12/22/2008 | PLUMBING - GAS PRESS TEST FNL | Partial Approval | IVRS - Inspection :* GAS TO NEW UNITS PHASE 1 OK |
|
| 12/11/2008 | PLUMBING - GAS PRESS TEST FNL | Partial Approval | IVRS - Inspection :* POST BOND FOR GAS |