Inspection Status: Approved
Inspection History: ELECTRIC - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/21/2009 | ELECTRIC - FINAL | Approved | IVRS - Inspection :* | |
| 07/15/2009 | ELECTRIC - FINAL | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1) GROUNDS AND NEUTRALS TO BE SEPERATE IN TRANSFER SWITCH 2) ALL CONDUCTORS OF FEEDER TO BE ROUTED TOGETHER. THIS INCLUDES EQUIPMENT GROUND. NEEDS TO BE ROUGHTED THRU SAME PINCHED KNOCKOUT IN PANEL 3) OPEN WIRING COMPARTMENT IN GENERATOR 4) OPEN 50 KVA TRANSFORMER FOR INSPECTION |
|