Inspection Status: Approved
Inspection History: PLUMBING - PROGRESS
Permit Number - T08CM01037
Inspection Description - PLUMBING - PROGRESS
Inspection Status - Approved
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/28/2009 | PLUMBING - PROGRESS | Approved | ||
| 05/21/2009 | PLUMBING - PROGRESS | Partial Approval | IVRS - Inspection :* | |
| 05/13/2009 | PLUMBING - PROGRESS | Partial Approval | IVRS - Inspection :* 1) WEST HALF PLUMBING OK FOR USE |
|
| 05/04/2009 | PLUMBING - PROGRESS | Partial Approval | IVRS - Inspection :* CLOSET FLANGES 2ND. PHASE OK TO COVER |
|
| 02/24/2009 | PLUMBING - PROGRESS | Partial Approval | IVRS - Inspection :* BELOW FLOOR WATER PIPING OK TO COVER |
|
| 01/22/2009 | PLUMBING - PROGRESS | Partial Approval | IVRS - Inspection :* | |
| 01/21/2009 | PLUMBING - PROGRESS | Partial Approval | ||
| 01/16/2009 | PLUMBING - PROGRESS | Partial Approval | IVRS - Inspection :* FLEX AT FURN. EXTEND VENT ABV AIR INLET PLUG ABANDON VENT CAPS ON FIXTURES NOT YET INSTALLED |
|
| 01/12/2009 | PLUMBING - PROGRESS | Partial Approval | IVRS - Inspection :* CLOSET FLANGES OK |
|
| 11/12/2008 | PLUMBING - PROGRESS | Not ready for Inspection | IVRS - Inspection :* REDLINE ANY CHANGES TO GAS SYSTEM SUPPORT PIPING AT RISER TO ROOF A PLAN REVISION IS REQUIRED FOR ADDITIONAL GAS FIXTURE |
|
| 07/08/2008 | PLUMBING - PROGRESS | Denied | IVRS - Inspection : See detailed listing on site.| 999* PLEASE HAVE ROUGH SOIL ADDED TO PERMIT. INSTALLATION OF DRAIN PIPING FOR P-8 DENTAL CHAIRS, APPEARS TO BE IN VIOLATION OF SECTION 1001.4 AND 1003.3 PROVIDE A DETAIL OF DENTAL UNIT WASTE AND WATER CONNECTIONS. A PRODUCT LISTING AND MANUFACTURE INSTALLATION INSTRUCTIONS MAY BE HELPFUL BACKFLOW PROTECTION MAY BE REQUIRED FOR EACH WATER CONNECTION. |