Inspection History Details
Inspection Status: Approved
Inspection History: BUILDING PRE-SLAB
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/13/2008 | BUILDING PRE-SLAB | Approved | IVRS - Inspection :* OK TO POUR MECHANICAL PAD |
|
| 06/12/2008 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* OK TO POUR LOADING DOCK DRIVEWAY & SIDEWALK |
|
| 05/21/2008 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* CURB AND NOSE OF DOCK NE RAMP ON LOADING DOCK |
|
| 05/16/2008 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* OK TO POUR LOADING DOCK #4 -- 12" OC INSTALLING CURB 2 BARS |
|
| 05/14/2008 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* OK TO POUR EQUIPMENT PAD EXTENSION EXTRA #4's ADDED |
|
| 05/13/2008 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* #4's 18 O.C FOR NEW A/C POD EXTENSION EPOXY REBAR SPECIAL INSPECTED NEEDS TO MATCH ENGINEERED RFI |