Inspection History Details
Inspection Status: Approved
Inspection History: BUILDING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/30/2009 | BUILDING - FINAL | Approved | IVRS - Inspection :* 1) ALL TRADES AND FIRE FINALS ARE COMPLETE |
|
| 06/25/2009 | BUILDING - FINAL | Not ready for Inspection | IVRS - Inspection :* CANCELED BY CONTRACTOR |
|
| 03/13/2009 | BUILDING - FINAL | Partial Approval | IVRS - Inspection :* ALL TRADES ARE COMPLETE OK TO OPEN UNDER CURRENT TEMP C OF O |
|
| 03/11/2009 | BUILDING - FINAL | Not ready for Inspection | IVRS - Inspection :* NEED PLUMBING FINAL |
|
| 03/06/2009 | BUILDING - FINAL | Partial Approval | IVRS - Inspection :* OK FOR APPLICATION OF "C OF O" (TEMPORARY) FOR MOVING IN OF EQUIPMENT AND FURNITURE - NOT FOR OCCUPATION FIRE, ELECTRIC, MECHANICAL, PLUMBING - OK FOR TEMP C OF O |
|
| 03/04/2009 | BUILDING - FINAL | Not ready for Inspection | IVRS - Inspection :* INFO. ONLY |