Inspection History Details
Inspection Status: Approved
Inspection History: MECHANICAL - PROGRESS
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/19/2008 | MECHANICAL - PROGRESS | Approved | IVRS - Inspection :* - FLUE PIPE ON REZNOR FURNACE IN WRONG DIRECTION OF FLOW - REMOVE GAS PIPE SUPPORT FROM UNIT - SEAL DUCT AND PROVIDE DAMPER IN TECH. ROOM OK FOR TILES |
|
| 06/13/2008 | MECHANICAL - PROGRESS | Partial Approval | IVRS - Inspection :* 1. INSTALL FLEX DUCT PER DETAIL (2/M3.1) 2. PROVIDE TIE WIRES TO STRUCTURE ON REGISTERS OVER 25 POUNDS LESS THAN 25 POUNDS CAN TIE TO GRID SYSTEM 3. SEAL EXHAUST DUCT ABOVE GRID 4. INSULATE RETURN CANS ABOVE GRID 5. PROVIDE CORRECT DIFFUSERS IN RESTROOMS 6. SEAL AROUND DUCTS PENETRATING WALLS PER PLANS 7. REMOVE FOIL TAPE FROM FLUE PIPE 8. PROVIDE DAMPERS IN EXHAUST DUCT PER PLANS |