Permit: T08CM00304

Parcel: 12701003S

Inspection Status: Approved

Inspection History: EXCAVATION/LAYOUT REBAR & ZON

Permit Number - T08CM00304

Inspection Description - EXCAVATION/LAYOUT REBAR & ZON

Inspection Status - Approved

Date Description Inspector Results Comments
06/19/2008 EXCAVATION/LAYOUT REBAR & ZON Approved IVRS - Inspection :*
PHASE IV COMPLETE - OK TO POUR 11 @ CAISSON COLUMN FOOTINGS
06/18/2008 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
CONTRACTOR CANCELED
06/16/2008 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
CONTRACTOR CANCELED
06/03/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
SW CANOPY -- 13 @ CAISSON COLUMN FOOTINGS (STEEL) PLACEMENT PHASE IV -- OK TO POUR COLUMN FOOTINGS
05/19/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1ST 20 SPACES @ REAR EAST PARKING LOT ON WEST SIDE
NORTH END #5
05/02/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
CAISSON EXCAVATIONS & STEEL COLUMN PLACEMENT @ SHADE STRUCTURES #4, 6, 8 AND 10
05/01/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
05/01/2008 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
PHASE IV

*SECTION 1 (NORTH) CAISSON #1 -- NEED 3" CLEARANCE OF COLUMN FROM EMBANKMENT; SECTION 3 (SOUTH) CAISSON #4
PROPER CLEARANCE OF 3" NEEDED
04/08/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
PHASE III -- 7 @ CAISSON COLUMN FOOTINGS
#7 COLUMN (FURTHEST SOUTH)
NEED MINIMUM 3" CLEARANCE FROM EMBANKMENT
OK TO POUR PROGRESS AREAS
03/20/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
9 @ CAISSON FOOTINGS & COLUMNS, PHASE II
OK TO POUR

*PLEASE LEAVE PERMIT & PLANS @ JOB SITE
03/04/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
PHASE I; CAISSON FOOTINGS @ 6'
AS PER CHANGE DATED 27 FEB O8 -- OK TO POUR