Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/08/2010 | PLUMBING - FINAL | Approved | PER INSP COPY | |
| 01/07/2010 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection :* | |
| 12/21/2009 | PLUMBING - FINAL | Partial Approval | IVRS - Inspection :* 1) 2ND AND 3RD FLLOR COMPLETE 2) 1ST FLOOR COMMON AREAS, LAUNDRY AND MECHANICAL ROOM COMPLETE |
|
| 12/18/2009 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection :* 1) 2ND AND 3RD FLOOR ONLY, ALL FIXTURES ARE TO BE ON AND FUNCTIONAL 2) 3RD FLOOR-FLOOR SINK MISSING STRAINER |
|
| 12/08/2009 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection :* | |
| 12/03/2009 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection :* 1) CALL IN AND HAVE APPROVED, ALL REQUIRED INSPECTIONS PRIOR TO CALLING FINAL 2) YOU ARE NOT READY FOR FINAL INSPECTION |
|
| 11/25/2009 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection :* | |
| 11/23/2009 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection :* |