| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/25/2009 | EXCAVATION/LAYOUT REBAR & ZON | Approved | IVRS - Inspection :* | |
| 02/06/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* CONTINUOUS FOOTING @ N/E CORNER RETAINING WALL |
|
| 09/25/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* ALL CONTINUOUS FOOTINGS AND SPREAD FOOTING AT NORTH END OF GYM BLDG. EXCEPT TOE DOWN INTERIOR WALL FOOTINGS TO BE POURED LATER |
|
| 07/07/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* FOOTING WALL @ EAST SIDE OF ROOM #105 (W-5) |
|