Inspection Status: Approved
Inspection History: REINFORCED MASONRY PRE-GROUT
Permit Number - T08CM00039
Inspection Description - REINFORCED MASONRY PRE-GROUT
Inspection Status - Approved
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/18/2009 | REINFORCED MASONRY PRE-GROUT | Approved | IVRS - Inspection :* | |
| 03/02/2009 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* TAPERED EXTERIOR COLUMNS #4 & 5 @ 12'4" OK TO GROUT |
|
| 02/27/2009 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* EXTERIOR TAPERED COLUMNS (NORTH) #1, 2, 3 @ 8'; #4, 5 @ 8'8" - OK TO GROUT (DETAIL #115; PAGE S4.1) |
|
| 02/26/2009 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* NORTHSIDE COLUMNS #1 THRU #5 @ 56" -- OK TO GROUT |
|
| 02/17/2009 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* STAIRWELL WALLS; MECHANICAL ROOMS TOPPED OUT OK TO GROUT - SPECIAL INSPECTED |
|
| 02/12/2009 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) NORTH WALL AT 20'-32'; STAIRWELL (EAST & WEST) WALLS AT 31'-OK TO GROUT PROGRESS AREAS |
|
| 02/11/2009 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* WEST MECH/ELEC #202 WALL @ 28'-32' (32'8" CENTER PORTION); EAST WALL @ 28'-32'; ENSURE PROPER PLACEMENT OF VERTICAL REBARS -- OK TO GROUT PROGRESS AREAS |
|
| 02/10/2009 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* STAIRWELL WALL (EAST) @ 12'8" AFFE MEZZANINE; NORTH EXTERIOR WALL (NORTH) FROM STAIRWELL TO EAST WALL @ 28' OK TO GROUT |
|
| 02/09/2009 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* EAST MEZZANINE WALL @ 12' AFFE; STAIRWELL @ 12' ABOVE FLOOR FINISHED (2ND FLOOR); NORTH WALL #107 @ 24'-28' OK TO GROUT PROGRESS AREAS |
|
| 02/06/2009 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* SOUTH WALL (INFILL) TOPPED OUT @ 35'4" -- OK TO GROUT |
|
| 02/04/2009 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* ROOM #104, WEST & NORTH WALLS @ 20'-24'; ROOM #101 N.WALL @ 20'-24'; STAIRWELL WALLS @ 8'8" AFFE MEZZANINE OK TO GROUT PROGRESS AREAS ENSURE PROPER PLACEMENT OF REBAR |
|
| 02/03/2009 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* STAIRWELL (EAST WALL) @ 4'8" ABOVE 2ND FFE; 2ND FLOOR EXTERIOR WALLS; N, E, W @ 16'-20' OK TO GROUT PROGRESS AREAS |
|
| 01/30/2009 | REINFORCED MASONRY PRE-GROUT | Not ready for Inspection | IVRS - Inspection :* | |
| 01/29/2009 | REINFORCED MASONRY PRE-GROUT | Partial Approval | SOUTH EXTERIOR WALL (INFILL) @ 20'8"-24'8" OK TO GROUT PROGRESS AREAS |
|
| 01/28/2009 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* SOUTH EXTERIOR WALL (INFILL) @ 16'8" TO 20'8" OK TO GROUT |
|
| 01/27/2009 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* SOUTH EXTERIOR WALL (IN-FILL) @ 12'8"-16'8"; JANITOR ROOM EAST WALL @ 10'4"; STORAGE #111 EAST WALL TOPPED OUT - OK TO GROUT PROGRESS AREAS |
|
| 01/26/2009 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* SOUTH WALL (INFILL) 8'-12' CORRECTION OF HEAD JOINT MADE @ 10' SPECIAL INSPECTION; JANITOR ROOM #110 EAST WALL @ 8'-12' OK TO GROUT |
|
| 01/23/2009 | REINFORCED MASONRY PRE-GROUT | Not ready for Inspection | IVRS - Inspection :* WILL RECALL FOR 1/27 |
|
| 01/22/2009 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* SOUTH EXTERIOR WALL (INFILL) @ 4'-8' OK TO GROUT RESTROOMS - EAST WALL - TOPPED OUT @ 10' OK TO GROUT |
|
| 01/21/2009 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* EAST RESTROOM WALL @ 8'8"; STORAGE ROOM #112 WEST WALL @ 12'8"; JANITOR ROOM #110 EAST WALL @ 0'-4' EXTERIOR SOUTH WALL (SE PORTION) @ 0'-4' OK TO GROUT PROGRESS AREAS |
|
| 01/16/2009 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* EAST WALL OF RESTROOMS #113-114 @ 56" WEST VESTIBULE WALL @ 16'4" -- OK TO GROUT PROGRESS AREAS* *SPECIAL INSPECTION REPORT #2948JA080 1/14/09 CORRECTIONS COMPLETED 1/16/09 |
|
| 01/15/2009 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* RESTROOM WALLS (EAST) #113 & 114 @ 8'8" - 12'8"; WEST RESTROOM WALL #113; WEST RISER ROOM WALL #109: 8'8"-12'8" OK TO GROUT |
|
| 01/13/2009 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* RESTROOM #105 WEST WALL @ 4'8" TO 8'8"; STORAGE ROOM #112 - EAST WALL @ 4'8" - 8'8" OK TO GROUT |
|
| 01/12/2009 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* TREATMENT AREA #101 WEST & NORTH WALLS TOPPED OUT @ 17'4"; NORTH EXTERIOR WALL @ HYDRO ROOM #107 TO STORAGE (EAST) ROOM #112 @ 15'4"; RESTROOM #105 (WEST) @ 4' -- OK TO GROUT PROGRESS AREAS |
|
| 01/07/2009 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* PERIMETER WALLS @ 8'-12'; INTERIOR WALLS BATHROOMS AND INTERIOR STAIRWELL @ 13'8" -- OK TO GROUT PROGRESS AREAS |
|
| 01/05/2009 | REINFORCED MASONRY PRE-GROUT | Not ready for Inspection | IVRS - Inspection :* CONTRACTOR CANCELED -- RAINED OUT |
|
| 12/30/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) INTERIOR CMU STAIRWELL WALLS (E & W) AT 4'-8' OK TO GROUT |
|
| 12/29/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) PERIMETER CMU WALLS EXCEPT ON EAT AND WEST ENDS AND INTERIOR CMU WALL AT ROOMS #110, 111, 112, 113, 114, 109, 106 & 115 OK TO GROUT-SPECIAL INSPECTED |
|
| 12/19/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 4' NORTHERN SECTION |
|
| 09/03/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* SE CORNER LOBBY CMU WALLS @ 12'-16' OK TO GROUT PROGRESS AREA |
|
| 09/02/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* NORTH INTERIOR GYM WALL TOPPED OUT @ 34'4"; LOBBY; SE WALL @ 8' - 12' OK TO GROUT PROGRESS AREAS |
|
| 08/29/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* NORTH GYM WALL @ 28'-32'; SOUTH GYM WALL @ 24' 50' TO 70' WEST OF S.E CORNER EAST GYM WALL PIERS TOPPED OUT @ 29'4" INTERIOR TROPHY CASE WALLS @ 4' - 8' OK TO GROUT PROGRESS AREAS |
|
| 08/27/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* NORTH GYM WALL @ 24'8" - 28'8" (CENTER PORTION) 4 @ VENTS WITH LENTELS ABOVE WEST GYM WALL PIERS @ 24'8" TO 29'4"; (SOUTH WALL NOT READY) - OK TO GROUT PROGRESS AREAS |
|
| 08/25/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* SOUTH GYM WALL (CONSTRUCTION ACCESS) WEST APPROX. 32' @ 28'8" -- OK TO GROUT PROGRESS AREA |
|
| 08/22/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* NORTH INTERIOR GYM WALL - APPROX. 80' FROM NW CORNER @ 20'8" TO 24'8" * WEST GYM WALL @ 20'8" TO 24'8" * SOUTH GYM WALL APPROX. 45' FROM SW CORNER @ 20'8" - 24'8" -- OK TO GROUT PROGRESS AREAS |
|
| 08/20/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* N.E CORNER OF NORTH INTERIOR WALL & EAST GYM WALL @ 20'8" OK TO GROUT |
|
| 08/18/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* NE CORNER GYM AREA @ 17'6"; PERIMETER GYM WALLS @ 20'8" EXCEPT NW CORNER (GROUTED @ 17'6") OK TO GROUT PROGRESS AREAS |
|
| 08/13/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* WEST GYM WALL @ 16'8"; NORTH INTERIOR WALL @ 16'8"; SW WALL OF ROOM #102 @ 16'8" -- OK TO GROUT |
|
| 08/12/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* NORTH INTERIOR WALL @ 12'8" (EXCEPT NE CORNER) SOUTH WALL (GYM) WEST TO EAST FROM SW CORNER APPROX. 45' @ 16'8" -- OK TO GROUT NW STORAGE ROOM #102 - SW WALL @ 8'8" -- OK TO GROUT |
|
| 08/11/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* SOUTH GYM WALL @ SE CORNER APPROX. 20' @ 16'8" EAST GYM WALL NE APPROX. 16' @ 16'8" OK TO GROUT PROGRESS AREAS |
|
| 08/08/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* WEST WALL (ALL); S. GYM WALL 0-20' E OF SW CORNER; 27-50' - E - OF SW CORNER; N.WALL @ 0-12' E OF NW CORNER ALL HEIGHTS @ 8'7" TO 12'7" E.WALL 3' SOUTH OF NE CORNER TO 4' NORTH OF SE CORNER @ 12'7" TO 16'7" GROUTED & SPECIAL INSPECTED |
|
| 08/06/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) EAST WALL AT 12'; NW INTERIOR WALLS AT FIRST TWO; LINTELS AT 8'; SW. EXTERIOR WALL AT ROOM #101 AT 4' SE LOBBY EXTERIOR WALL AT 4'-OK TO GROUT PROGRESS AREAS |
|
| 08/04/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* EXTERIOR CMU WALLS - WEST, EAST, SOUTH @ 4'-8' OK TO GROUT PROGRESS AREAS |
|
| 07/31/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* NORTH INTERIOR WALL @ SW CORNER OF ROOM #102 TO ENTRY DOOR #100G @ 0'-4' OK TO GROUT |
|
| 07/30/2008 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* EAST, WEST & SOUTH WALLS (EXTERIOR) @ 0' - 4' OK TO GROUT PROGRESS AREAS |