Inspection History Details
Inspection Status: Cancelled
Inspection History: PLUMBING - ROUGH, SOIL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/20/2008 | PLUMBING - ROUGH, SOIL | Cancelled | IVRS - AP canceled | |
| 06/19/2008 | PLUMBING - ROUGH, SOIL | Cancelled | IVRS - AP canceled | |
| 06/12/2008 | PLUMBING - ROUGH, SOIL | Partial Approval | 1. REVIEWED PLUMBING INSTALLATION IN MASONRY WALLS WILL RECHECK EXPOSED PIPING ON INTERMEDIATE 2. OK TO COVER PVC BETWEEN 2 WAY C.O AND INTERCEPTORS |
|
| 06/11/2008 | PLUMBING - ROUGH, SOIL | Approved | ||
| 04/08/2008 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 1. SEWER CONNECTION MADE OK 2. ABS DWV UNDER SLAB OK TO COVER |