Inspection Status: Approved
Inspection History: ENGINEERING PRE-CONSTRUCTION
| Date |
Description |
Inspector |
Results |
Comments |
| 05/07/2010 |
ENGINEERING PRE-CONSTRUCTION |
|
Approved |
|
| 05/06/2010 |
ENGINEERING PRE-CONSTRUCTION |
|
Cancelled |
IVRS - AP canceled |
| 03/19/2010 |
ENGINEERING PRE-CONSTRUCTION |
|
Partial Approval |
FINAL INSPECTION. CONTRACTOR NEEDS TO COMPLETE PUNCH LIST ITEMS #1, 2, 3 ON THE PUNCH LIST PROVIDED TO THEM ON 3/2/10. CALL IN FOR INSPECTION WHEN ITEMS ARE COMPETE. |
| 09/04/2009 |
ENGINEERING PRE-CONSTRUCTION |
|
Approved |
MET WITH JERRY (331-2261) FOR PRE-CON. HIRED COMPANY TO PLACE STORMWATER CONTROLS, THEY WILL GO UP ON TUESDAY. |