Permit: T08BU01925

Parcel: 132191120


Addresses:

2345 E IRVINGTON RD


Inspection Status: Approved

Inspection History: ENGINEERING PRE-CONSTRUCTION

Permit Number - T08BU01925

Inspection Description - ENGINEERING PRE-CONSTRUCTION

Inspection Status - Approved

Date Description Inspector Results Comments
12/29/2009 ENGINEERING PRE-CONSTRUCTION Approved
12/23/2009 ENGINEERING PRE-CONSTRUCTION Partial Approval PARTIAL APPROVAL GIVEN FOR STOCKING PURPOSES. REMAINING PUNCH LIST ITEMS STILL NEED TO BE ADDRESSED, ALONG WITH SLOW PERKING BASIN ON E/S OF BUILDING.
12/10/2009 ENGINEERING PRE-CONSTRUCTION Not ready for Inspection SPOKE WITH CONTRACTOR. MISTAKENLY CALLED IN FINAL INSPECTION. INSPECTION INTENDED FOR RIGHT-OF-WAY INSPECTOR.
12/09/2009 ENGINEERING PRE-CONSTRUCTION Not ready for Inspection PRELIMINARY PUNCH LIST.

Address: 2345 E. Irvington Rd Permit #: T08BU01925 Contractor: Jerry Jerry1@haworthcorp.com

Preliminary Punch List

The following is a preliminary list of items that need to be addressed prior to site completion. This list was requested by the contractor prior to final inspection. Due to on-going construction not all inspections were possible. As construction nears completion the contractor will call for a final inspection to address outstanding items.

Contractor needs to complete all site work per approved plan.

1) Compete basin structure on S/E corner of property per approved plan and in accordance with standards.
2) Clean basin structure on the east side of building so that outlet pipe is clear of debris and basin is draining properly. Certified letter from engineer is necessary for all basins/drainage structures on the property.
3) H/C parking on south-side of building needs to be verified @ 2%, unable to verify at time of inspection due to placement of construction materials.
4) Ensure that all sidewalk scuppers are cleared of dirt and debris
5) Remove all construction debris
6) Stabilize all areas disturbed by construction,
7) Complete all landscaping items.
8) Complete necessary striping per approved plan
9) Install bicycle parking per approved plan
10) Remove stormwater controls from site
11) Per note 27 complete installation of air compressor and bollard
12) Per note 32 complete the access ramp to basin
13) Provide as-builts where necessary

Please call if you have any questions or need clarification. M. Carreon 240-9971
08/18/2009 ENGINEERING PRE-CONSTRUCTION Approved MET WITH JERRY (602)332-5023 ON SITE. DISCUSS HIS SWPPP, WILL BE INSTALLING CONTROLS LATER THIS WEEK. BLDG. COMPLETION DATE SET FOR DEC. 24TH.