Permit: T08BU01907

Parcel: 99999999A


Addresses:

2396 E RIVER RD


Inspection Status: Approved

Inspection History: STORMWATER FOLLOW-UP INSP

Permit Number - T08BU01907

Inspection Description - STORMWATER FOLLOW-UP INSP

Inspection Status - Approved

Date Description Inspector Results Comments
04/23/2010 STORMWATER FOLLOW-UP INSP Approved
03/25/2010 STORMWATER FOLLOW-UP INSP Continued CONTRACTOR NEEDS TO ADDRESS TRACKING FROM NON-PAVED SIDE OF SITE TO PAVED SIDE.

ONE HALF OF SITE WILL BE OCCUPIED WITH A FENCE DIVIDING CONSTRUCTION FROM PUBLIC, THIS MUST BE MAINTAINED THROUGHOUT CONSTRUCTION
NO OTHER SIGNIFICANT STORM WATER CONCERNS AT THIS TIME
03/10/2010 STORMWATER FOLLOW-UP INSP Continued NO CONCERNS AT THIS TIME
03/01/2010 STORMWATER FOLLOW-UP INSP Continued NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME
02/17/2010 STORMWATER FOLLOW-UP INSP Continued CONTRACTOR WILL WANT C OF O FOR NORTH BLDG FIRST.
SIDEWALK, CURBING AND TRASH ENCLOSURE INSTALLED. NORTH RETAINING WALL COMPLETED. CONCERNS ABOUT BIKE PARKING TYPE AND LOCATIONS. SITE NOT PAVED YET.
NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME
01/12/2010 STORMWATER FOLLOW-UP INSP Continued SOME CURBING, AND SIDE WALK INSTALLED ALONG BLDG TO NORTH. NO OTHER SITE WORK COMPLETED. SIGNIFICANT GRADE CHANGES THROUGHOUT THE PROJECT, WILL INSPECT FOR COMPLIANCE.
NO STORM WATER CONCERNS AT THIS TIME
01/06/2010 STORMWATER FOLLOW-UP INSP Continued CONTRACTOR WORKING ON SOME SITE WORK, MOSTLY COMPLETING BLGD CONSTRUCTION.
NO STORM WATER CONCERNS AT THIS TIME
10/02/2009 STORMWATER FOLLOW-UP INSP Continued NO STORM WATER CONCERNS AT THIS TIME. CONTINUE TO SWEEP UP ADJACENT ROADWAYS AND DOCUMENT SELF INSPECTIONS.
08/14/2009 STORMWATER FOLLOW-UP INSP Continued 1) REPLACE OR RE-ESTABLISH SEDIMENT CONTROLS THAT HAVE FILLED-IN OR LOST MORE THAT 50% OF THIER EFFECTIVENESS (SOUTH END OF SITE).
2) ADD SUPPLEMENTAL CONTROLS ALONG THE EAST/SE PERIMETER OF THE SITE WHERE THE GRADE ON SITE IS HIGHER THAN OFF SITE.
3) BRING ANY SPOILS FROM TRENCHING BACK ONTO SITE
06/11/2009 STORMWATER FOLLOW-UP INSP Continued STORM WATER ITEMS LISTED ON PREVIOUS INSPECTION HAVE BEEN ADDRESSED.
CONCRETE/MATERIALS WASH OUT HAS BEEN INSTALLED.
NO OTHER SIGNIFICANT STORM WATER CONCERNS AT THIS TIME.
06/01/2009 STORMWATER FOLLOW-UP INSP Correction Required 1) RE-ESTABLISH YOUR CONSTRUCTION ENTRANCE
2) SWEEP UP TRACKED SOIL
3) ENSURE PERIMETER SEDIMENT CONTROLS ARE AT THE PERIMETER - AND ARE NOT COVERED WITH FILL DIRT
4) POST A SIGNED COPY OF YOUR NOI AT ENTRANCE