Inspection History Details
Inspection Status: Approved
Inspection History: STORMWATER FOLLOW-UP INSP
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/28/2012 | STORMWATER FOLLOW-UP INSP | Approved | ||
| 12/15/2010 | STORMWATER FOLLOW-UP INSP | Continued | NO CONCERNS AT THIS TIME. | |
| 12/15/2010 | STORMWATER FOLLOW-UP INSP | Continued | NO CONCERNS AT THIS TIME. | |
| 06/23/2010 | STORMWATER FOLLOW-UP INSP | Continued | NO CONCERNS AT THIS TIME. SITE UNDER VARIOUS STAGES OF CONSTRUCTION AT THIS TIME, AN INTERMEDIATE GRADING INSPECTION CAN BE SCHEDULED AT THIS TIME. SIDEWALKS, PAVEMENT, AND DRIVEWAYS ARE ALMOST FULLY COMPLETE. | |
| 01/21/2010 | STORMWATER FOLLOW-UP INSP | Continued | NO CONCERNS AT THIS TIME. | |
| 09/21/2009 | STORMWATER FOLLOW-UP INSP | Correction Required | Minor cleanup & check SWPPP controls for repairs | |
| 03/24/2009 | STORMWATER FOLLOW-UP INSP | Partial Approval | NO CONCERNS CONTROLS IN PLACE AND BEING MAINTAINED |
|
| 03/05/2009 | STORMWATER FOLLOW-UP INSP | Correction Required | TRACK OUT NEEDS TO BE SWEPT UP | |
| 03/02/2009 | STORMWATER FOLLOW-UP INSP | Scheduled | CALLED CHRIS AT 904-0563 AND RESCHEDULED FOR 3/3 | |
| 02/26/2009 | STORMWATER FOLLOW-UP INSP | Correction Required | HEAVY TRACK OUT FROM WATER TRUCK ADAM WITH GREENRIDGE ADVISED IT MUST BE CLEANED UP HAULING WORK IS BEING DONE ON S SIDE OF LOTS BETWEEN LOT 27 AND LOT 34 V-DITCH HAS BEEN INSTALLED ALONG N SIDE OF LOT |