Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T08BU01755

Parcel: 12904157A


Addresses:

2121 E BROADWAY BL


Inspection Status: Approved

Inspection History: GRADING - INTERMEDIATE

Permit Number - T08BU01755

Inspection Description - GRADING - INTERMEDIATE

Inspection Status - Approved

Date Description Inspector Results Comments
07/19/2010 GRADING - INTERMEDIATE Approved
07/07/2010 GRADING - INTERMEDIATE Partial Approval OK to pave parking area.
06/01/2010 GRADING - INTERMEDIATE Continued 1) CONTRACTOR MOVED CONSTRUCTION ENTRACE, SITE STILL NOT PAVED.
2) SOME SIDEWALKS AND CURBING COMPLETED, SCUPPERS BEING INSTALLED.
3) CONTRACTOR NEEDS TO CLEAN OUT STORM DRAINAGE SYSTEM AND PROTECT ALL INLETS AND CATCH BASINS FROM SOIL AND CONST DEBRIS.
4) CONTRACTOR NEEDS TO CLEAN UP MATERIALS DUMPED ON SITE ( PAINT, STUCCO...).
COTRACTOR MAY NEED TO SUBSTITUTE SOME TREES SHOWN ON LANDSCAPE PLAN DUE TO THE FACT THAT THEY ARE TOO CLOSE TO THE BLDG. MAY NEED REVISED PLAN.
04/07/2010 GRADING - INTERMEDIATE Continued NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME.
NO SITE WORK HAS BEEN COMPLETED, CONTRACTOR STATED HE WILL CALL IN AN INSPECTION WHEN SUB FOR SITE WORK HAS STARTED.
02/17/2010 GRADING - INTERMEDIATE Continued NORTH PERIMETER WALL HAS BEEN INSTALLED W/ WALL OPENINGS.
UNDERGROND DRAINAGE W/ BUBBLER HAS BEEN INSTALL, NO OTHER SITE WORK COMPLETED.
NO STORM WATER CONCERNS AT THIS TIME
01/06/2010 GRADING - INTERMEDIATE Continued WORK BEING DONE ON BLDGS, SOME SITE WORK COMPLETED LIKE BACK WALL W/ WALL OPENINGS AND SOME CURBING. STORM WATER DRAINAGE BUBBLER HAS BEEN COVERED TO PROTECT IT FROM SOIL.
NO OTHER SIGNIFICANT STORM WATER CONCERN
12/29/2009 GRADING - INTERMEDIATE Continued SITE WORK NOT COMPLETED, NO SIGNIFICANT CJANGES TO THE APPROVED PLANS
11/03/2009 GRADING - INTERMEDIATE Continued TOOK PICS OF BUBBLER CULVERT PIPE AT OUTLET OF STORM DRAIN SYSTEM
10/29/2009 GRADING - INTERMEDIATE Continued INSPECT INSTALLATION OF CONCRETE AREA DRAINS ALONG STORM DRAINAGE SYSTEM.
LAUREN W/ ENG APPROVED CHANGE FROM PLASTIC TO CONCRETE DRAINS, WILL GET COPY OF EOR APPROVAL AND COT APPROVAL FOR CHANGE
10/27/2009 GRADING - INTERMEDIATE Continued TALKED W/ SUPER ON CHANGE FROM PLASTIC CATCH BASINS SHOWN ON APPROVED PLANS TO CONCRETE CATCH BASINS. CONTRACTOR WILL PROVIDE APPROVAL FROM EOR AND COT.
10/23/2009 GRADING - INTERMEDIATE Continued CONTRACTOR INSTALLED APPROX. 200' OF 18" HDPE STORM DRAIN PIPE W 6 AND 8" INLET "T" SECTIONS FOR ROOF LEADERS AND AREA DRAINS. PIPE TRENCH WAS BEDDED, GRADED TO DRAIN AND COMPACTED. TERMINATION POINT IS A BUBBLER BOX INTO A RET/DET BASIN.
PROVIDE ENG OF RECORD APPROVAL OF CHANGE FROM CATCH BASIN SHOWN ON GRADING PLAN TO PROPOSED CONCRETE CATCH BASINS - CALL FOR INSPECTION PRIOR TO COVER OF CATCH BASIN/PIPE CONNECTIONS.
ITEMS LISTED ON PREVIOUS INSPECTION HAVE BEEN ADDRESSED.
CONTINUE TO MAINTAIN, INSPECT, AND REPLACE SEDIMENT CONTROLS THROUGHOUT THE DURATION OF THE PROJECT PER YOUR STORM WATER PLAN.