Permit: T08BU01755

Parcel: 12904157A


Addresses:

2121 E BROADWAY BL


Inspection Status: Approved

Inspection History: STORMWATER FOLLOW-UP INSP

Permit Number - T08BU01755

Inspection Description - STORMWATER FOLLOW-UP INSP

Inspection Status - Approved

Date Description Inspector Results Comments
08/10/2010 STORMWATER FOLLOW-UP INSP Approved
07/19/2010 STORMWATER FOLLOW-UP INSP Continued CONTRACTOR HAS A TEMP USE PERMIT TO OCCUPY THE ADJOINING PROPERTY TO THE SOUTH DURING CONSTRUCTION, THIS PARCEL MUST BE STABILIZED IN ACCORDANCE WITH THE GRADING ORDINANCE PRIOR TO FINAL APPROVALS.

NO STORM WATER CONCERNS AT THIS TIME.
CONTRACTOR STATED THAT THE SITE WILL BE COMPLETED WITHIN TWO WEEKS.
06/01/2010 STORMWATER FOLLOW-UP INSP Continued 1) CONTRACTOR MOVED CONSTRUCTION ENTRACE, SITE STILL NOT PAVED.
2) SOME SIDEWALKS AND CURBING COMPLETED, SCUPPERS BEING INSTALLED.
3) CONTRACTOR NEEDS TO CLEAN OUT STORM DRAINAGE SYSTEM AND PROTECT ALL INLETS AND CATCH BASINS FROM SOIL AND CONST DEBRIS.
4) CONTRACTOR NEEDS TO CLEAN UP MATERIALS DUMPED ON SITE ( PAINT, STUCCO...).
COTRACTOR MAY NEED TO SUBSTITUTE SOME TREES SHOWN ON LANDSCAPE PLAN DUE TO THE FACT THAT THEY ARE TOO CLOSE TO THE BLDG. MAY NEED REVISED PLAN.
04/07/2010 STORMWATER FOLLOW-UP INSP Continued NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME.
NO SITE WORK HAS BEEN COMPLETED, CONTRACTOR STATED HE WILL CALL IN AN INSPECTION WHEN SUB FOR SITE WORK HAS STARTED.
03/19/2010 STORMWATER FOLLOW-UP INSP Continued NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME
03/10/2010 STORMWATER FOLLOW-UP INSP Continued NO CONCERNS AT THIS TIME
02/17/2010 STORMWATER FOLLOW-UP INSP Continued NORTH PERIMETER WALL HAS BEEN INSTALLED W/ WALL OPENINGS.
UNDERGROND DRAINAGE W/ BUBBLER HAS BEEN INSTALL, NO OTHER SITE WORK COMPLETED.
NO STORM WATER CONCERNS AT THIS TIME
01/06/2010 STORMWATER FOLLOW-UP INSP Continued WORK BEING DONE ON BLDGS, SOME SITE WORK COMPLETED LIKE BACK WALL W/ WALL OPENINGS AND SOME CURBING. STORM WATER DRAINAGE BUBBLER HAS BEEN COVERED TO PROTECT IT FROM SOIL.
NO OTHER SIGNIFICANT STORM WATER CONCERNS
12/29/2009 STORMWATER FOLLOW-UP INSP Continued NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME. ENSURE SEDIMENT CONTROLS ARE MAINTAINED THROUGHOUT THE PROJECT.
11/03/2009 STORMWATER FOLLOW-UP INSP Continued NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME
10/29/2009 STORMWATER FOLLOW-UP INSP Continued NO STORM WATER CONCERNS AT THIS TIME
10/23/2009 STORMWATER FOLLOW-UP INSP Continued CONTRACTOR INSTALLED APPROX. 200' OF 18" HDPE STORM DRAIN PIPE W 6 AND 8" INLET "T" SECTIONS FOR ROOF LEADERS AND AREA DRAINS. PIPE TRENCH WAS BEDDED, GRADED TO DRAIN AND COMPACTED. TERMINATION POINT IS A BUBBLER BOX INTO A RET/DET BASIN.
PROVIDE ENG OF RECORD APPROVAL OF CHANGE FROM CATCH BASIN SHOWN ON GRADING PLAN TO PROPOSED CONCRETE CATCH BASINS - CALL FOR INSPECTION PRIOR TO COVER OF CATCH BASIN/PIPE CONNECTIONS.
ITEMS LISTED ON PREVIOUS INSPECTION HAVE BEEN ADDRESSED.
CONTINUE TO MAINTAIN, INSPECT, AND REPLACE SEDIMENT CONTROLS THROUGHOUT THE DURATION OF THE PROJECT PER YOUR STORM WATER PLAN.