Inspection Status: Approved
Inspection History: GRADING - FINAL
| Date |
Description |
Inspector |
Results |
Comments |
| 04/22/2020 |
GRADING - FINAL |
|
Approved |
SITE APPEARS TO HAVE BEEN CONSTRUCTED PER THE APPROVED PLANS |
| 12/12/2011 |
GRADING - FINAL |
|
Partial Approval |
SITE IS ALMOST COMPLETE AT THIS TIME. A CERTIFICATION LETTER NEEDS TO BE PROVIDED FROM THE ENGINEER OF RECORD ALONG WITH APPROVED AS-BUILT DRAWINGS FOR THIS SITE PRIOR TO SCHEDULING THE FINAL GRADING INSPECTION. |
| 12/09/2011 |
GRADING - FINAL |
|
Partial Approval |
LOOKED OVER THE SITE TOO SEE IF ALL OF THE WORK HAD BEEN COMPLETED. CREWS ARE STILL COMPLETING ALL OF THE LANDSCAPING, AND WORKING ON THE PIA PORTION WITH TRANSPORTATION. I HAVE ASKED THE CONTRACTOR TO PROVIDE ME WITH THE APPROVED AS-BUILT DRAWINGS SO THAT I CAN MAKE THE FINAL INSPECTIONS TO CLEAR THIS PERMIT. |