Inspection History Details
Inspection Status: Approved
Inspection History: GRADING - INTERMEDIATE
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/19/2009 | GRADING - INTERMEDIATE | Approved | ||
| 02/05/2009 | GRADING - INTERMEDIATE | Correction Required | MET WITH ENG OF RECORD DISCUSSED REQUIREMENTS FOR ENGINEERING APPROVAL OF GRADING AND BLDG PERMITS. 1) PROVIDE AN APPROVED/REVISED GRADING, DEVELOPEMENT, AND SITE PLAN SHOW ALL CHANGES MADE TO THE ORIGINAL PLANS. 2) COMPLETE ALL SITE WORK PER THE REVISED PLANS. 3) ACCESS RAMP ALONG THE NORTH END OF THE WAREHOUSE BLDG MEETE ADAAG AND ANSI FOR SLOPE AND WIDTH REQUIREMENTS. 4) HC RAMP ALONG FRONT OF BLDG TO PARKING AREA OK FOR SLOPE, WIDTH, AND TRUNCATED DOMES. |
|
| 01/28/2009 | GRADING - INTERMEDIATE | Continued | TALKED WITH ENGINEER ABOUT CHANGES TO APPROVED GRADING AND DEVELOPMENT PLANS. | |
| 01/08/2009 | GRADING - INTERMEDIATE | Correction Required | SPOKE WITH ARCHITECH HE STATED THAT HE WOULD ADD A PEDESTRIAN REFUGE AREA TO TIE INTO EXISTING WALKWAYS DURING PHASE II OF THE PROJECT. HE ALSO STATED THAT HE WOULD CHANGE THE GRADING PLAN TO SHOW WHAT WORK WILL BE COVERED UNDER PHASE I/ PHASE II | |
| 01/06/2009 | GRADING - INTERMEDIATE | Correction Required | 1) PROVIDE AN APPROVED PLAN THAT SHOWS WHAT WORK WILL BE COMPLETED UNDER PHASE I AND PHASE II OF THIS PROJECT. 2) PROVIDE A DESIGNATED PEDESTRIAN CIRCULATION PATH FROM THE RIGHT OF WAY TO THE BLDG. 3) ENSURE YOU PROVIDE A RET/DET BASIN CERT STATEMENT FROM THE ENG OF RECORD STATING THAT ALL BASINS AND DRAINAGE WAYS WERE BUILT PER THE APPROVED PLAN. |